Lien Waiver Form

Enter your email below to download the file.

By downloading, you agree to receive marketing emails from Mastt. Unsubscribe anytime.

Oops! Something went wrong while submitting the form.
Free Template

Lien Waiver Form

Four lien waiver forms in Word, plus the owner-side workflow that stops you paying twice. Conditional before the money clears, unconditional after, with a log that tracks every tier.

Templates
Word Template
Excel Template
Powerpoint Template
Lien Waiver Form
Template by
Jackson Row
Published:
May 26, 2024
Updated:
August 26, 2026

What is a Lien Waiver?

A lien waiver is a document in which a contractor, subcontractor, supplier or equipment lessor gives up its right to place a mechanics lien on a property, in exchange for payment. The claimant signs it. The owner collects it.

The same document is called a lien release, a waiver of lien, or a waiver and release. The lien release form entry covers the terminology.

For an owner or the project manager acting for one, collecting waivers is a payment control rather than paperwork. Lien rights belong to each claimant individually, so a release from the general contractor does not release the subcontractor two tiers below who filed a preliminary notice.

Lien Waiver Form Example

Here's an example of a completed lien waiver form, a conditional waiver on final payment signed by a general contractor for $248,317.40.

Completed conditional lien waiver form example on final payment with exclusions listed, signature and notary acknowledgment.
Lien waiver form example showing a conditional waiver and release on final payment with exclusions listed.

The Four Types of Lien Waiver

Two questions produce four forms: does the release take effect on signature or when payment clears, and does it cover one payment period or the whole job?

  1. Conditional waiver and release on progress payment. Releases nothing until the payment clears. Require it before you release a progress payment.
  2. Unconditional waiver and release on progress payment. Effective the moment it is signed, paid or not. Require it after the progress payment has cleared.
  3. Conditional waiver and release on final payment. Releases everything once final payment clears. Require it before you release final payment including retainage.
  4. Unconditional waiver and release on final payment. The end of the claimant's lien rights on the project. Require it after final payment has cleared in full.

Conditional before the money clears, unconditional after. Taking the unconditional form early never helps the owner; it creates a claimant who has released rights without being paid.

Partial means the same as progress: one payment period, with retainage and later work intact. Final covers the whole job.

Two mistakes recur. Issuing unconditional waivers too early, and using a final waiver while retainage or a pending change order is still outstanding.

What's Included in This Lien Waiver Form

Four forms to print and issue, plus the guidance to know which one to require and when.

Part What it holds
Form 1 Conditional waiver and release on progress payment.
Form 2 Unconditional waiver and release on progress payment.
Form 3 Conditional waiver and release on final payment.
Form 4 Unconditional waiver and release on final payment.
Which waiver to require, and when The six-step owner-side sequence from payment application through to cleared funds.
Seven ways an owner pays twice Each failure as a mechanism, ordered by how often it happens.
The waiver log Tier, claimant, notice on file, waiver due, through date, amount and status.
The statutory states What each statute actually changes, beyond supplying wording.
What "substantially comply" is testing Wording, type size, notice language, timing and who may require what.

Every form carries the same fields: project, owner, claimant and its role, the through date or date of last work, the amount, and an excluded from this release block. Anything not listed in it is released, so disputed claims, pending change orders, unbilled work, delay claims and retainage all have to be written in.

Forms 3 and 4 include a notary acknowledgment, to complete only where the state or the contract requires it.

States That Require a Statutory Lien Waiver Form

Twelve states prescribe lien waiver wording by statute: Arizona, California, Florida, Georgia, Massachusetts, Michigan, Mississippi, Missouri, Nevada, Texas, Utah and Wyoming. What the statute does varies, so check your own state's text rather than assuming.

Two examples, read from the state's own source:

State Statute What the statute says
California Civ. Code §§ 8124, 8132, 8134, 8136, 8138 To be effective, a waiver and release must substantially follow one of four statutory forms. A conditional release binds only where there is evidence of payment, meaning an endorsed check paid by the bank or a written acknowledgment from the claimant.
Florida Fla. Stat. § 713.20 Provides forms for progress and final payment. Subsection (6) prohibits requiring a lienor to furnish a different form, and subsection (2) makes any waiver signed in advance unenforceable. Subsection (8) states that a non-conforming waiver is still enforceable on its own terms.

Get the current statutory form from the state itself or its licensing board, not from a template library. Statutes are amended and forms are revised.

Substantial compliance can test more than wording. Some states also constrain type size, require specific notice language verbatim, or set when the release takes effect. Retyping a form from a template library is not the same as using the statutory one.

How to Fill Out a Lien Waiver Form

Build the collection list from the preliminary notices you received, not the contracts you signed. That is the only list that includes every party who can lien you.

  1. Log every party that can lien the property, including sub-subcontractors and suppliers who sent a notice to owner or notice of furnishing.
  2. When a payment application arrives, note the period it covers and the amount claimed, since the waiver has to match both.
  3. Require a conditional progress waiver from each claimant before you pay, because they can sign it safely and most will without argument.
  4. Check the through date and the amount against the payment application before the money moves.
  5. Release funds.
  6. Require an unconditional progress waiver once funds have cleared, not once they have been sent.
  7. At final payment, run the same two steps again: conditional before, unconditional after.
  8. Copy the claimant's legal entity name exactly as it appears on its notice, since a release signed by "Vance Mechanical" does not obviously release a lien claimed by "Vance Mechanical Inc."
  9. List everything the release does not cover in the exclusions block.
  10. Keep the log current, because your lender and title company will audit it.

Where a lower-tier subcontractor will not provide a waiver, a check made jointly to it and the party above it puts the money where the lien risk sits.

Common Lien Waiver Mistakes

Most lien waiver failures come down to two things: collecting from the wrong list of parties, or taking the unconditional form before the money has cleared. Both leave an owner exposed to a claimant who can still lien the property after being paid.

  • You collected the general contractor's waiver, paid, and a subcontractor liened you anyway. Lien rights belong to each claimant individually.
  • You accepted an unconditional waiver against a payment that had not cleared. It is effective on signature, so if the payment is stopped or reversed the claimant has released rights it was never paid for, and that is the position it will litigate.
  • The through date is earlier than the period you paid for. A waiver releases claims only through the date written on it. Pay an application covering July against a waiver dated 30 June and one month is unreleased.
  • You took a final unconditional waiver while retainage was still outstanding. This harms the claimant, which is exactly why it costs you.
  • The waiver was written into the subcontract before the work started. A waiver signed in advance is void by statute in Georgia and unenforceable in Florida.
  • The waivers track the base contract and nobody collected one for the change orders. Change orders are often billed and approved separately.
  • You used your own form in a state that prescribes one. In Florida, requiring a form other than the statutory one is prohibited outright.

Build the collection list from the preliminary notices you received rather than the contracts you signed, and never take an unconditional waiver before funds clear. Those two controls prevent most of the list above.

Related Articles and Templates

Explore these resources for lien waivers, pay applications, progress payments, and payment certification:

FAQs About Lien Waiver Forms

The claimant signs it, never the owner. That means the general contractor, subcontractor, sub-subcontractor, material supplier or equipment lessor, and anyone else with lien rights against the property. The owner's job is to require it, check it and file it.
An unconditional waiver is, because it states the claimant has been paid. A conditional waiver is not, because it takes effect only when the payment named on it clears the bank. That difference is why an unconditional waiver should never be signed before funds clear.
Twice per payment. Conditional with the payment application before you pay, unconditional once the funds have cleared. Then the same pair again at final payment, with retainage included in the final amount.
Usually not. Mississippi and Wyoming require it, and Texas did until 2022, which is why older guidance still lists three states. Beyond those, a construction contract or a lender's draw package can require notarization regardless of what the state says, and a document being recorded may need it for the recorder to accept it. Check both.
Florida does not require a waiver, but it does control the form. Its statute sets out waiver forms for progress and final payments and says nobody may require a lienor to furnish a different form. That restriction has limited force in practice, because the same statute makes a waiver that is not substantially similar to those forms enforceable on its own terms anyway. What is not negotiable is timing: a waiver of lien rights signed in advance is unenforceable.
Generally yes. Electronic signatures are broadly recognized, but a state that prescribes the form may also prescribe how it is executed, and a notarization requirement changes the answer. Confirm against the statute and the contract before moving a project to e-signature.
No. It releases lien, stop payment notice and payment bond rights only. A delay claim, change order dispute or warranty obligation needs a separate release.
Rarely, because there is generally no mechanics lien against public property. The equivalent security is a payment bond, and bond claim procedures and deadlines work differently.

General information only, not legal advice. Lien rules vary by state and change.

Topic: 
Lien Waiver Form

Written by

Jackson Row

Jackson Row joined Mastt's founding North American team in 2023, implementing the platform for US government agencies and Fortune 500 organizations. He holds a Bachelor of Engineering in civil and mining engineering from UNSW and began his career as a construction cadet on civil projects in Sydney. At Mastt, he contributes articles on payment and client-side project management.

LinkedIn Icon
Back to top