Restaurant Construction Guide: Cost, Timeline, and Tips

Restaurant construction is building a space to cook and serve food. Get steps, costs, and tips to plan and finish your restaurant build right.

Popular

Use this FREE Commercial Construction Budget Template to plan and track project costs—break down expenses by trade, phase, and cost code for clear budget control and reporting.

Restaurant Construction
Back to top

Restaurant construction is a complex process that blends design, code compliance, technical systems, and operational flow into a single build. Unlike other commercial construction, it requires early decisions that are hard to change later.

In this guide, you'll get a step-by-step view of how to build or renovate a restaurant, including how to choose a site, estimate costs, and manage timelines through to opening. It's designed to give restaurant owners and project teams the tools to deliver a fully functional space that’s inspection-ready and built for service.

TL;DR
Restaurant construction turns an empty space into a fully functioning restaurant built for service, safety, and flow. Pick the right site, lock in your budget, and design for kitchen efficiency and code compliance. Hire a contractor who knows restaurants, manage permits early, and keep your timeline tight to open on budget.

What is Restaurant Construction?

Restaurant construction is the process of building or transforming a space into a fully functioning restaurant. It includes everything needed to support food service, from installing kitchen equipment and setting up plumbing to finishing the dining area and making sure the restaurant building meets health and safety codes.

This type of commercial project is tailored to how restaurants actually work. It focuses on creating a space that’s efficient for staff, comfortable for guests, and aligned with the restaurant concept. Every detail, from kitchen layout to lighting, plays a role in bringing the dream restaurant to life.

Why Restaurant Construction is Unique

Restaurant construction stands apart from other commercial construction projects because it combines complex technical demands with high expectations for guest experience. Each restaurant construction project must align safety regulations, kitchen efficiency, and interior design in one tightly coordinated effort.

This type of project brings together functional and regulatory requirements that shape every stage of the construction process:

  • Building Codes Compliance: Restaurants must meet strict health, fire, accessibility, and mechanical building codes from multiple authorities.
  • Operational Efficiency: Kitchen layout, equipment placement, and workflow directly affect staff performance and service speed.
  • Guest Experience: Lighting, acoustics, and seating layout contribute to comfort, brand identity, and the overall dining experience.

What makes this even more demanding is how much of the outcome is locked in early. Unlike offices or retail construction, restaurants offer little flexibility once core systems are built.

Changes later in the construction can be costly and disruptive, so success depends on getting the details right from the start. Tools like Mastt help teams align these diverse priorities through centralized planning, risk tracking, and construction monitoring.

5 Steps to Restaurant Planning and Construction

To plan restaurant construction effectively, you need to set the foundation before anything is built. That starts with defining your concept, building the right team, and designing a space that actually works.

Each of these steps shapes how smoothly your restaurant project moves from idea to execution.

Step 1. Define Your Concept and Goals

Defining your concept and goals means deciding what kind of restaurant you’re opening and how it should function. This guides every part of your restaurant construction plan, from layout to kitchen equipment to dining experience.

The right restaurant concept gives your team something solid to build around:

  • Brand Direction: Be specific about the kind of dining experience you’re creating and how that should come through in the layout, materials, and mood of the space.
  • Customer Experience: Think through how people will enter, order, eat, and move through the commercial space.
  • Operational Priorities: Decide how much space each area needs to support daily service.

If you're leasing a space, your vision also has to fit within the limits of the building and your lease agreement. Some concepts may require layout changes, mechanical upgrades, or permits your landlord won’t cover, so it’s important to check what’s possible before locking in your plan.

Step 2. Assemble Your Project Team

Assembling your restaurant construction project team means hiring professionals who understand the pace, pressure, and precision of restaurant construction services. You want experienced restaurant contractors who’ve done this before and who can work well together.

This type of build depends on clear coordination across several roles:

  • Restaurant Architect: Converts your vision into practical, code-compliant plans.
  • Interior Designer: Shapes the look and feel of the space while ensuring it aligns with your layout and budget.
  • Construction Project Manager: Oversees timelines, approvals, budgets, and team coordination.
  • Restaurant Contractor / General Contractor: Runs the build and manages subcontractors on-site.
  • Specialized Consultants: Bring technical expertise for commercial kitchens, lighting, HVAC, and more.

A good team is about how they collaborate under pressure. Early coordination reduces risk, speeds up decision-making, and keeps everyone aligned.

Step 3. Design for Workflow, Systems, and Code

Designing for workflow, systems, and code means making sure the space works just as well during a busy shift as it does on paper. That takes practical planning.

Good restaurant design supports real-world performance through three core areas:

  • Kitchen Workflow: Lay out stations for prep, cook, and service to minimize back-of-house friction.
  • System Planning: Account for HVAC, hood systems, grease traps, power needs, and plumbing.
  • Code Requirements: Meet all fire, health, accessibility, and building codes from the start.
  • Sustainable Systems: Consider energy-efficient equipment, low-flow fixtures, and sustainably sourced materials. These choices can reduce utility costs, improve ventilation performance, and may help qualify for local green building incentives or rebates.

Design decisions are hard to reverse once systems go in. Thinking through function and compliance early in the design phases gives you a space that’s efficient, safe, and inspection-ready.

Step 4. Choose the Right Construction Delivery Method

Choosing the right restaurant construction delivery method means deciding how your construction project will be structured from design through build. Different project delivery methods affect how you communicate, manage costs, and keep the schedule on track.

The most common delivery formats for restaurant remodeling and new construction are:

  • Design-Bid-Build: Design is completed, then bids are collected. Good for price control, slower overall.
  • Design-Build: One firm handles design and construction. Faster but requires strong trust.
  • Construction Manager at Risk: CM joins early, oversees budget and timeline, and guarantees price.

Each approach has trade-offs. If you want more price control and are okay with a longer process, design-bid-build works.

If speed and simplicity matter most, a design-build firm might be better. For more hands-on oversight, consider hiring a construction management team that stays involved from design through closeout.

Step 5. Plan for Permits and Approvals Early

Planning for permits and approvals early means building time into your schedule for reviews, revisions, and follow-ups. Skipping this step is one of the fastest ways to delay your new restaurant opening.

Most restaurant construction projects need signoff from several authorities before construction begins:

  • Health Department: Reviews commercial kitchen layout, food safety zones, and sinks.
  • Building Department: Checks structural plans, HVAC, egress, and plumbing.
  • Fire Marshal: Inspects sprinklers, hoods, alarms, and emergency access.

In a leased space, you may also need your landlord to approve restaurant construction drawings or submit documents to the city on your behalf. Build time into your schedule for these back-and-forths, especially if your landlord manages commercial spaces or requires third-party consultants.

Most delays happen because early decisions didn’t match what the space could actually support. In leased restaurant spaces, that gap between vision and feasibility can quietly grow until it costs time and money. Planning well means pressure-testing your ideas against the realities.

📑 Expert Tip: Ask building management if they require specific drawing formats or have design manuals. These often include rules for file types, signage, venting, and approved contractors.

How to Choose the Right Site and Lease

To choose the right site and lease, evaluate how well the space supports your restaurant concept, meets infrastructure needs, and aligns with the lease terms. Focus on areas like location quality, restaurant building feasibility, and landlord flexibility.

Every site decision has long-term impact on cost, buildability, and operations. The key factors to evaluate are:

Factor What to Look For Why It Matters
Location Foot traffic, parking, visibility, access, zoning Affects sales, branding, and long-term growth
Audience Fit Area demographics, dining habits A mismatch can limit repeat business
Building Readiness HVAC, plumbing, electrical, hood, grease trap Saves on upgrades and shortens build time
Kitchen Venting Access for Type 1 hood or exhaust Needed for bar construction and hot kitchens, costly to retrofit
Structural Limits Floor load, ceiling height, egress, ADA compliance Affects layout, kitchen equipment, and code approval
Permit History Prior food use, permit records Can speed up approvals and reduce inspection issues
Shared Systems Venting, water/gas access, noise impact Limits upgrades and layout options in multi-tenant commercial spaces
TI Allowances Landlord contribution toward buildout Offsets restaurant construction costs, helps stretch budget
Landlord Approvals Who approves plans, vendors, timeline Delays here can stall your schedule
Lease Terms Term, escalation, exclusivity, rent start Affects cash flow, budget, and opening runway
Change Limits Rules on signage, outdoor seating, equipment May restrict brand visibility or operations

Before committing, walk the site with your architect and restaurant contractor to identify system gaps, and bring in a real estate lawyer to review terms that affect restaurant remodeling or renovation services.

Use what you find to renegotiate responsibilities, deadlines, or buildout allowances. A great location means little if the lease terms or infrastructure hold you back.

New Restaurant Construction vs. Remodels

Choosing between a new construction and a restaurant remodel depends on how much flexibility, time, and capital you have to work with. Evaluate how each option affects infrastructure, landlord control, and long-term cost.

Here’s a breakdown to help you compare both options side by side:

Category New Construction Remodel / Second-Gen Buildout
Infrastructure Built from scratch, no existing systems. Work around existing plumbing, HVAC, and kitchen layout.
Permitting Full plan review, more inspections. Faster if use is unchanged.
Timeline 6–12+ months with full sitework. Quicker if major upgrades aren’t needed.
Cost Higher, especially with utilities or shell work. Lower initial costs, but surprises can add up.
Design Flexibility Full control over layout, restaurant design, finishes. Limited by structure and landlord rules.
Landlord Involvement More freedom in shell or ground-up builds. Often requires approved vendors and phased access.
Downtime Risk None because the site starts empty. May need off-hours work or phased restaurant renovation.

Before you commit, walk the space with your architect, restaurant contractor, and landlord. Clarify what can change, what’s restricted, and how your timeline lines up with rent commencement. It’s easier to adapt a plan than undo surprises once the construction process begins.

Factors Affecting Restaurant Construction Costs

To estimate restaurant construction costs with accuracy, focus on the factors that carry the biggest budget impact. Prioritize areas like space condition, kitchen equipment, and utility upgrades.

Some cost drivers vary widely by project and location. The most impactful ones for a restaurant owner are:

Cost Driver Considerations Typical Range / Impact
Space Condition Shell vs. second-generation restaurant building Shell: $300–$600/sf, Second-gen: $150–$300/sf
Kitchen Equipment New vs. reused, standard vs. custom $50,000–$250,000+ depending on scope
Utilities & Systems Electrical, plumbing, HVAC, fire suppression $50,000–$150,000 for upgrades in older or shell commercial spaces
Finish Level Flooring, lighting, millwork, acoustics Budget: $50–$100/sf, Premium: $100–$200/sf
Permitting & Fees City/health permits, fire marshal, impact fees; landlord-required approvals $5,000–$50,000+, often delayed by building condition or lease terms
Design & Consulting Architect, interior designer, consultants 5–15% of total construction cost
Contingency Buffer Change orders, delays, price fluctuations 5–10% of total construction cost
Tenant Improvement Allowances Landlord contribution toward construction costs Typically $10–$40/sf, varies by lease terms

Cost overruns usually come from the details no one confirmed early. Before you budget, walk the site with your contractor and compare your plans to what the space can actually support. Using a construction cost estimator during early planning can help identify potential cost overrun risks.

Grease trap access, insufficient electrical service, or shared venting systems can all shift your budget fast and rarely in your favor. The earlier you catch it, the more control you keep over your restaurant construction project.

Disclaimer: Cost ranges provided are estimates only and will vary significantly based on location, market conditions, site condition, and project complexity. Always consult your contractor and consultants for detailed pricing.

How to Handle Restaurant Codes and Compliance

To handle restaurant construction codes and compliance, build them into your construction concepts early. Start with five critical steps: call your local authorities, hire professionals, map inspection phases, confirm lease-related constraints, and document every approval along the way.

These actions will help you avoid delays, rework, and missed opportunities during your commercial construction build:

  • Call Local Authorities Before You Draw: Reach out to the building, health, and fire departments before finalizing plans. Knowing their requirements early can save weeks in permitting.
  • Hire Pros Who Know the Rules: Bring in an architect, interior designer, or consultant who’s worked with your local agencies. They’ll catch red flags like ADA access, egress paths, venting, or fire and life safety systems.
  • Map Your Inspection Timeline: List every required inspection by phase (e.g., rough plumbing, final health), and match them to your schedule. Some inspections may pass with conditions that require follow-up fixes. Know what’s allowed to open and what must be resolved first.
  • Check Lease Restrictions: Some landlords restrict signage, grease systems, venting routes, or equipment. Confirm what’s allowed in writing before you finalize construction drawings. In some leases, the landlord must approve your plans before you can submit to the city, verify this step early.
  • Track Approvals in Writing: Keep copies of all plan reviews, inspector notes, and approvals. If your plans get rejected or returned with corrections, have your restaurant design team walk you through each fix. Small misses here often lead to big delays later.

When you treat Authority Having Jurisdiction (AHJ) as partners and make code part of your restaurant design and construction management process, approvals move faster. The worst surprises usually come from guessing what’s allowed instead of confirming it early.

How to Hire the Right Restaurant Contractor

To hire the right restaurant contractor, ask questions that test for real experience, not just general qualifications. Focus on their track record with restaurants, how they handle permits and approvals, and how they manage cost and communication on tight timelines.

Use these questions and checks to evaluate your top contractor candidates:

  • Ask for Restaurant-Specific Experience: Request examples of restaurants they’ve built. Ask how they handled kitchen layout, fire suppression, and health inspections. Prioritize contractors who’ve worked on projects similar in scale and service model to yours.
  • Confirm Site Type Familiarity: Ask if they’ve built in spaces like strip malls, mixed-use buildings, or second-gen restaurant conversions. Follow up with questions about how they handled shared utilities, venting limitations, or aging infrastructure.
  • Check Their Permitting Process: Ask who on their team handles construction submittals, revisions, and re-inspections. Confirm whether they’ve worked with your local AHJs or dealt with tenant improvements in leased commercial properties.
  • Call Recent Clients: Ask for two restaurant client references and call them. Ask how the contractor handled change orders, missteps, or delays and whether they’d work with them again.
  • Review Budget Management Process: Ask how they present changes, what triggers change orders, and how fast pricing is turned around. Look for clear, written workflows.
  • Gauge Communication Style: Pay attention to how they respond during the interview. Are they organized? Direct? Willing to flag risks? If they’re scattered now, they’ll be scattered when it counts.

Don’t wait for problems to find out how your restaurant contractor thinks. You’re hiring someone to troubleshoot, communicate, and keep the restaurant construction project aligned with your goals. The right partner delivers quality commercial construction that brings your dream restaurant to life.

The Restaurant Construction Process

To understand the restaurant construction process, follow how the project moves from early planning to final handover. Break it into three clear phases: pre-construction, build-out, and closeout.

Each phase depends on different approvals, handoffs, and timing risks that, if missed, can delay your restaurant opening or increase costs.

1. Pre-Construction: Design, Permits, and Budget Setup

Pre-construction starts with setting the plan in motion. This includes finalizing drawings, securing permits, and confirming budgets. You’ll also coordinate with your landlord, interior designer, and restaurant contractor to align scope, responsibilities, and timelines before anything is built.

In a leased commercial space, this is also when you'll need to review landlord requirements, confirm any TI allowances, and get written approval on plans and schedules. Missing those steps here can delay permits and drive unexpected costs later in your restaurant construction project.

2. Build-Out: Construction, Trades, and Inspections

Build-out is when plans turn into physical progress on site. This phase includes demolition, framing, rough-ins for plumbing and electrical, installation of kitchen equipment, finishes, and inspections.

Your contractor manages day-to-day site activity, coordinating trades and sequencing work to match the schedule. Even well-planned restaurant construction services encounter snags.

Weather, delayed materials, or failed inspections can all impact progress, so ongoing construction project management is key.

3. Closeout: Final Inspections and Project Handover

Closeout is when the construction project shifts from building to preparing for opening. You’ll need to pass health, fire, and building inspections to get your certificate of occupancy. Any missed inspection or failed test at this stage can cause a schedule delay.

Once the restaurant building is approved, you can move in kitchen equipment, train staff, and prepare for launch. Your restaurant contractor will also hand over warranties, manuals, and any final paperwork during this phase.

Make sure everyone on your team knows who’s responsible for each phase and decision. Clear roles reduce confusion, avoid gaps, and keep the restaurant construction project moving when timelines are tight.

Tips on Managing the Restaurant Construction Timeline

To manage the restaurant construction timeline effectively, start by getting honest about where delays usually come from. Set clear expectations early for permits, material deliveries, and landlord approvals.

Restaurant construction projects move smoother when tasks are sequenced well, decisions are made early, and teams know what’s expected. These tips will help you avoid the bottlenecks that stall progress:

Pre-Construction: Set the Schedule Before You Start

Early planning sets the pace for everything that follows. These steps help you build a realistic schedule before commercial construction begins:

  • Map Your Permits: Track when plans need to be submitted, who approves them, and how long each agency typically takes. If a permit is delayed, re-sequence other non-permit-dependent tasks to keep momentum.
  • Lock In Landlord Steps: Ask for the landlord’s review process and timeline in writing, especially in malls or multi-tenant commercial spaces. If landlord signoff stalls, stay ahead by requesting all landlord timelines in writing.
  • Know When Rent Starts: Many leases don’t wait for your grand opening. Know the rent commencement date, and work backwards to build in time for approvals and punch list delays.
  • Check Building-Wide Constraints: Ask about restrictions tied to noise, shared utility access, or construction hours imposed by other tenants or building operations.

Construction: Keep Work Moving with Smart Planning

Once the build is underway, day-to-day progress depends on how well tasks are scheduled and how quickly decisions get made:

  • Sequence Tasks Thoughtfully: Some jobs depend on others finishing first. Know which tasks can overlap and which ones can’t (e.g., slab cutting before plumbing rough-ins).
  • Order Early, Not After Demo: Don’t wait to order long-lead items like walk-ins, vent hoods, or specialty lighting. If equipment or materials are delayed, look at temporary solutions or push less dependent areas forward.
  • Assign One Owner to the Timeline: Whether it’s your GC, construction manager, or restaurant owner’s rep, someone needs to track tasks and call out delays as soon as they come up.

Closeout & Launch: Prepare for Inspections and Opening

Finishing strong means building in space for inspections, training, and last-minute fixes. These steps help smooth the handoff from restaurant construction to operations:

  • Make the Weekly Meeting Count: Use your standing check-in to surface blockers, update deadlines, and adjust as needed. Keep it short, focused, and consistent.
  • Schedule Inspections Early: Book health and fire inspections in advance. Missing a window can set your restaurant opening back by weeks. If inspections fail, ask inspectors for detailed notes and reschedule quickly.
  • Give Yourself Breathing Room: Add buffer time for inspections, rework, or backorders. A few extra days now are cheaper than paying a team to wait later.
  • Plan for Training Time: Build in space for soft opening prep, staff onboarding, and final walkthroughs. Compressing these steps adds stress and lowers service quality on day one.

A missed delivery, delayed signoff, or forgotten permit can snowball fast especially when tied to lease milestones like rent commencement. The more visibility you give your construction timeline, the easier it is to act quickly.

To stay on track, give your team visibility over tasks, deadlines, and hold-ups. Mastt’s construction management software helps restaurant owners manage timelines, track long-lead items, and spot blockers early.

What to Check Before You Open Your Restaurant

Before opening your new restaurant, confirm construction is closed out, systems are working, and your space is ready to operate. Focus on three things: securing your certificate of occupancy, confirming functionality, and preparing your staff for real service.

These steps help ensure your handoff from restaurant construction to operations is clean and your launch goes smoothly:

  • Close Out Construction and Punch List: Walk the space with your restaurant contractor, mark any outstanding work, and get timelines for fixes. Many landlords require punch list signoff before releasing TI funds. Get everything documented before final payments.
  • Pass Final Inspections and Secure CO: Schedule health, fire, and building inspections in advance. Once passed, request your certificate of occupancy (CO) before opening to the public.
  • Test Systems and Utilities: Run full commercial kitchen tests, check HVAC airflow, verify hot water pressure, and confirm your hood and fire suppression systems pass testing. Confirm all utilities (power, gas, water) are active and in your name before inspection day.
  • Schedule a Final Clean and Setup: Hire a professional crew to deep-clean post-construction debris. Set up furniture, fixtures, and kitchen equipment only after all systems are tested and clear.
  • Train Staff in the Finished Space: Start training once the restaurant building is safe, clean, and operational. This helps your team learn workflows in real conditions and flags anything that needs adjustment.
  • Label and Organize Key Areas: Mark shelves, prep zones, and kitchen layout during setup. Clear labeling improves efficiency and prevents confusion during early service.
  • Prepare for Soft Launch Events: Run a friends-and-family night or invite-only preview. These trial services help you test timing, identify service gaps, and make real-time adjustments before full opening.

The last few weeks before opening are your reset point, your chance to catch what still isn’t working. Use this time to fix, fine-tune, and rehearse. A clean finish here saves weeks of frustration later.

Deliver the Restaurant You Planned

Building a restaurant is about making sure the finished space actually supports how your business runs. The most effective builds stay grounded in what the restaurant actually needs to function.

If you stay clear on those priorities from start to finish, you won’t just open a restaurant, you’ll open the one you meant to build.