Mastt Logo
Why
Product
Product Tour
A video of Mastt sofware showing a dashboard with a map, charts and visualizations for project progress and health
Explore Mastt
Watch how Mastt is used on $25bn+ of capital improvement portfolios
REPORTING PLATFORM
Dashboards & Reporting
Contracts & Payments
Budget & Forecasts
Risks & Opportunities
Schedule
Integrations
AI
Solutions
Use Cases
Capital Projects
Programs & Portfolios
Enterprise
roles
Project Consultants
Project Owners
Industries
Education
Transportation
Aviation
Events
Public Works
Civil
Utilities
Residential
Real Estate Development
Pricing
Customers
Resources
Learn
Free Templates
Download free tools, guides, checklists, plans and more
Dashboard Examples
Download free dashboards & reports
Articles
Learn about Construction Project Management best practices
Topics
Full guides on the important topics around construction management
Webinars
Watch ConTech in action
SUPPORT
FAQs
Get answers for common questions
Get Help
Expert coaching, technical support and guidance
Trust Center
Learn how we protect your data and privacy.
Log In
Australia / APAC
North America Region
MENA
Rest of World
Log InSee Product Tour
02 9133 4355
Talk to Sales
|
Log In
Australia / APAC
North America Region
MENA
Rest of World
Start for Free
Mobile Menu Icon
Resources
/
Glossary

Project Variance

Project variance measures the difference between planned and actual cost, schedule, and scope in construction projects, helping teams track performance and manage risks.

Topic: 
Project Controls

Contents

Example H2
Related blog post

Variance Analysis: Calculate, Track, Report [Free Calculator]

Learn how to calculate, track, and report variance analysis in project management. Use our free variance calculator to manage costs, schedules, and resources.

Project Variance: Definition, Types, Analysis, and Control

Project variance refers to the difference between planned project outcomes and actual results in terms of cost, schedule, and performance. It helps project managers track budget overruns, delays, and efficiency gaps, ensuring they take corrective actions early.

Popular
Free Template

Project Dashboard Template

Use this FREE Project Dashboard Template to track progress, budget, risks, and key milestones, all in one clear, easy-to-share report.

Use this Template

What is Project Variance in Construction?

Project variance in construction is the difference between what was planned and what actually happens in cost, time, or work. It shows if a project is over budget, delayed, or different from the original plan.

Variance can be positive (indicating the project is performing better than expected) or negative (signaling issues that need attention). Understanding project variance is essential for maintaining control over budgets, schedules, and resources in construction and project management.

For example, if a construction project was planned to be 50% complete but has only reached 40%, the schedule variance (SV) would be negative, indicating a delay.

Optimize Project Cost Management  

Types of Project Variance in Project Management

The main types of project variance are schedule variance, cost variance, scope variance, and resource variance. Other types, like quality, risk, and safety variances, also impact project success and need careful tracking.

  • Schedule Variance (SV): Shows if a project is ahead or behind schedule based on planned milestones.
  • Cost Variance (CV): Measures the difference between the estimated budget and actual spending.
  • Scope Variance: Happens when delivered work does not match the original project scope.
  • Resource Variance: Occurs when actual use of labor, materials, or equipment differs from the plan.
  • Quality Variance: Indicates differences between expected and actual quality standards.
  • Risk Variance: Tracks the gap between expected risks and actual project risks.
  • Cash Flow Variance: Shows mismatches between planned and actual cash inflows and outflows.
  • Performance Variance: Measures how actual work efficiency compares to expectations.
  • Contract Variance: Happens when actual project execution does not match contract terms.
  • Safety Variance: Identifies differences between planned and actual safety performance on-site.

Tracking these variances helps managers apply better project controls by spotting problems early. Using this data, they can adjust plans, improve resource use, and reduce project risks, keeping projects on time and within budget.

How to Calculate Project Variance

Project variance is calculated using standard formulas that compare planned vs. actual project performance. These calculations help measure cost overruns, schedule delays, and efficiency gaps. Earned Value Management (EVM) applies these formulas to track project performance and identify risks early.

Key Project Variance Formulas

  • Cost Variance (CV): Measures budget performance.
    Formula: CV = Earned Value (EV) - Actual Cost (AC)
    • Positive CV: Project is under budget.
    • Negative CV: Project is over budget, requiring cost control measures.
  • Schedule Variance (SV): Tracks if a project is ahead or behind schedule.
    Formula: SV = Earned Value (EV) - Planned Value (PV)
    • Positive SV: Project is ahead of schedule.
    • Negative SV: Project is behind schedule, requiring timeline adjustments.

EVM further introduces Cost Performance Index (CPI) and Schedule Performance Index (SPI) to measure efficiency:

  • CPI (EV ÷ AC): A value above 1.0 means the project is within budget, while below 1.0 signals cost overruns.
  • SPI (EV ÷ PV): A value above 1.0 means the project is ahead of schedule, while below 1.0 signals delays.

For example, if a construction project has a CPI of 0.8, it means only 80 cents of value is earned for every dollar spent, highlighting inefficiencies. Using EVM metrics, project managers can make data-driven decisions to adjust costs, schedules, and resource allocation before minor variances turn into major risks.

How to Analyze Project Variance

To analyze project variance, project managers and project controllers should review cost and schedule differences, find the causes, and predict future risks to keep the project on track. Regular cost risk analysis helps prevent cost overruns and delays, ensuring the project follows the budget and timeline.

Here are the key steps to analyze project variance:

  • Compare cost and schedule variance together: Check if delays are causing cost overruns or if budget issues are slowing progress.
  • Identify root causes: Find out if material costs, labor inefficiencies, or external factors are creating the variance.
  • Use forecasting models: Adjust future estimates based on past variances and predict potential risks before they escalate.
  • Monitor trends over time: Look for recurring variances that may indicate deeper process issues needing long-term solutions.
  • Assess financial risk impact: Analyze how cost variances affect cash flow and overall project funding to adjust financial strategies.

By integrating trend analysis and predictive variance forecasting, project controllers can proactively adjust budgets, refine cost estimates, and improve project decision-making.

How to Report Project Variance in Construction Project Management

To report project variance in construction, project managers and project controllers should track cost and schedule differences, analyze their impact, and communicate findings clearly. A well-structured report should explain what changed, why it happened, how it affects the project, and what corrective actions will be taken.

Here's how to create a clear and effective project variance report:

  1. Collect variance data: Track cost, schedule, and scope deviations using project controls software or manual logs.
  2. Compare actual vs. planned performance: Identify differences in spending, timeline, or work progress.
  3. Find the cause: Investigate reasons for the variance, such as material price changes, labor shortages, or unexpected delays.
  4. Assess financial and operational impact: Determine how the variance affects cash flow, resource allocation, and project funding to adjust financial plans.
  5. Suggest corrective actions: Recommend solutions like budget adjustments, resource reallocation, or schedule changes.
  6. Create a structured report: Include key data insights, variance trends, financial impact analysis, and an action plan.
  7. Share with stakeholders: Provide reports to project owners, financial teams, and executives to guide decision-making.

Project controllers rely on variance reports to forecast future risks, adjust financial strategies, and improve project controls. Regular variance reporting helps teams stay proactive, reduce risks, and ensure financial stability throughout the project.

Create Your Free Project Dashboards with Mastt Today

Budget Variance vs. Project Variance: Key Differences

Budget variance measures the difference between planned and actual project costs, while project variance tracks differences in cost, schedule, and overall project performance. Budget variance focuses only on financial deviations, whereas project variance provides a broader view of project health.

Factor Budget Variance Project Variance
Definition Difference between budgeted and actual costs. Difference between planned and actual project outcomes.
Scope Focuses only on financial performance. Covers cost, schedule, and performance deviations.
Calculation Budgeted Cost - Actual Cost Earned Value - Planned Value (Schedule) or EV - AC (Cost)
Impact Over-budget projects require financial adjustments. Projects behind schedule or inefficient need resource allocation changes.
Example If labor costs exceed the allocated budget, it results in negative budget variance. If a project is 40% complete instead of the planned 50%, it has negative project variance.

Budget variance deals strictly with financial performance, while project variance takes a holistic approach, considering timelines, efficiency, and cost impacts together.

How to Reduce and Manage Project Variance

To keep projects on track, project managers must track costs, monitor schedules, and make quick adjustments. Catching budget overruns and delays early helps prevent bigger issues later.

Here are the best ways to reduce project variance:

  • Set Realistic Baselines: Use past project data to create accurate budgets and schedules.
  • Use Automated Cost Tracking: Track costs in real time to catch overruns before they get worse.
  • Monitor Schedule Performance: Check milestones often to spot delays early and adjust work plans.
  • Conduct Variance Analysis Regularly: Review project data to find patterns and fix problems fast.
  • Apply Risk Mitigation Strategies: Plan ahead for high-risk areas to avoid unexpected costs or delays.
  • Improve Communication Between Teams: Keep project managers, contractors, and stakeholders working together to solve issues quickly.

For example, if material prices suddenly rise, cost tracking tools can flag the issue early. The project team can then negotiate better deals, adjust orders, or shift the budget to stay on track.

If labor shortages slow progress, managers can reschedule work, approve overtime, or bring in subcontractors to avoid delays.

Optimize Project Cost Management  

How Can Mastt Help Manage Project Variance?

Mastt helps project managers and project controllers track, analyze, and reduce project variance by providing real-time cost data, automated variance reports, and forecasting tools.

Here's how Mastt helps manage project variance:

  • Real-time cost tracking: Provides up-to-date financial data so teams can detect budget variances immediately and take corrective action.
  • Automated variance reporting: Identifies cost, schedule, and performance deviations without manual calculations, reducing reporting errors.
  • Forecasting tools: Uses past data and trends to predict future variances, helping teams adjust budgets and schedules proactively.
  • Integrated project controls: Combines cost management, schedule tracking, and variance analysis in one platform for better decision-making.
  • Financial impact analysis: Helps project controllers assess how cost variances affect cash flow and funding, supporting financial planning.
  • Data-driven decision-making: Provides clear dashboards and reports so managers can adjust strategies quickly to minimize risks.

For example, if material costs unexpectedly increase, Mastt flags the budget variance right away. The team can then renegotiate contracts, adjust procurement strategies, or reallocate the budget before the issue affects the project.

If a project is behind schedule, Mastt’s tracking features help managers reschedule tasks, optimize resource use, or adjust deadlines to avoid further delays.

Posts on this topic

Controls Chart in Project Management [Examples]
Project Controls

Controls Chart in Project Management [Examples]

Learn how a control chart works in project management with simple types, steps, and real examples from construction to track cost, quality, time, and safety.

Controls Chart in Project Management [Examples]

Arlene Hidalgo

How to Implement a Project Control System in Capital Projects
Project Controls

How to Implement a Project Control System in Capital Projects

See how to set up a basic project control system to help manage cost, time, and risk in capital projects using clear steps and simple processes.

How to Implement a Project Control System in Capital Projects

Arlene Hidalgo

Using S-Curve Analysis to Control Project Costs & Schedules
Project Controls

Using S-Curve Analysis to Control Project Costs & Schedules

Improve project results using s-curve analysis to control costs and schedules, track progress, avoid delays, and make smart project decisions fast.

Using S-Curve Analysis to Control Project Costs & Schedules

Arlene Hidalgo

Powering Construction Project Management with easy-to-use tools

Start for FreeWatch Product Tour
Mastt Logo
Stay up-to-date with Mastt:
You're in the loop
Oops! Something went wrong while submitting the form.

Solutions

Use Cases

Managing Contract Variations
Project Timeline Management
Managing Construction Contracts
Client Dashboard
Construction Client Management
All Use Cases

Product

Dashboards & ReportingBudget & ForecastsRiskScheduleContracts & PaymentsIntegrationAll Features

Industries

Education
Transportation
Aviation
Events
Public Works
Civil
Utilities
Residential
Real Estate Development
All Industries

Customers

Featured CustomerSuccess Stories

Compare

Mastt vs ProcoreMastt vs KahuaMastt vs InEightMastt vs AconexMastt vs iTWOcx

Resources

Free TemplatesWebinarsGlossaryArticlesTopicsFAQProject Management FirmsRisksHelp Pages

Company

AboutAboutConstruction Project ManagementContact UsPrivacyLegalSecurity
© Copyright 2025 Mastt.
Be part of our community
LinkedIn Icon