Mastt Logo
Why
Product
Product Tour
A video of Mastt sofware showing a dashboard with a map, charts and visualizations for project progress and health
Explore Mastt
Watch how Mastt is used on $25bn+ of capital improvement portfolios
REPORTING PLATFORM
Dashboards & Reporting
Contracts & Payments
Budget & Forecasts
Risks & Opportunities
Schedule
Integrations
Solutions
Use Cases
Capital Projects
Programs & Portfolios
Enterprise
roles
Project Consultants
Project Owners
Industries
Education
Transportation
Aviation
Events
Public Works
Civil
Utilities
Residential
Real Estate Development
Pricing
Customers
Resources
Learn
Free Templates
Download free tools, guides, checklists, plans and more
Dashboard Examples
Download free dashboards & reports
Articles
Learn about Construction Project Management best practices
Topics
Full guides on the important topics around construction management
Webinars
Watch ConTech in action
SUPPORT
FAQs
Get answers for common questions
Get Help
Expert coaching, technical support and guidance
Trust Center
Learn how we protect your data and privacy.
Log In
Australia / APAC
North America Region
MENA
Rest of World
Log InSee Product Tour
02 9133 4355
Talk to Sales
|
Log In
Australia / APAC
North America Region
MENA
Rest of World
Start for Free
Mobile Menu Icon
Resources
/
Glossary

ROM Cost

ROM costs are early guesses of how much a project might cost before planning starts. See how to use, make, and improve ROM costs for real projects.

Topic: 
Construction Estimating

Contents

Example H2
Related blog post

What is ROM (Rough Order of Magnitude) & How to Use It

A rough order of magnitude is a quick way to estimate project costs early. Check how to use it, calculate ranges, and apply it in real construction work.

What is ROM Cost in Construction? Definition, Use Cases, & Best Practices

A ROM cost, or Rough Order of Magnitude cost, is a high-level estimate used early in construction projects across sectors like infrastructure, education, and healthcare. Common in planning and feasibility stages, it helps teams decide if an idea is financially viable, using past project data, benchmarks, or unit costs to guide early funding, scope, and approval conversations.

Popular
Free Template

Construction Cost Tracker

Use this FREE Construction Cost Tracker template for clear, efficient oversight of your capital project's financials.

Use this Template

ROM Cost Meaning

A ROM cost, or Rough Order of Magnitude cost, is a high-level estimate used in the early stages of a construction project. It provides a quick ballpark figure to assess whether a project idea is financially viable before detailed planning begins.

ROM costs typically fall within a wide accuracy range of -25% to +75%. They're based on limited information, such as past projects, unit costs, or conceptual plans, and serve as a starting point for decision-making, budgeting, or funding discussions.

Optimize Project Cost Management  

What is the Purpose of a ROM Cost?

ROM costs help teams make fast, informed decisions about whether to proceed with a project concept. They're commonly used before a design exists or when funding bodies need a quick value reference.

Here’s why ROM costs matter in construction:

  • Screen project feasibility: Check whether a concept aligns with available budgets.
  • Support early approvals: Provide financial inputs for stakeholder or board decisions.
  • Enable initial scope discussions: Guide early alignment on scope, size, and delivery options.
  • Inform procurement models: Help evaluate whether to use D&C, CM, or design-bid-build.
  • Start high-level funding strategies: Enable grant applications, PPP considerations, or internal budgeting.

Without a ROM cost, early decisions can be faulty. This often leads to costly rework or even project abandonment later.

When Do You Use a ROM Cost?

Use a ROM cost during the concept or initiation phase. This is before the design starts, consultants are hired, and timelines are fixed.

Here are common use cases for ROM cost estimates:

  • Strategic planning across public infrastructure portfolios
  • Business case development for government programs
  • Preliminary discussions with investors or funding authorities
  • Site selection or asset redevelopment studies
  • Comparing alternatives for build vs. refurbish options

ROM costs answer one early question: “Is this project worth exploring further?” They give a quick estimate to help decide if the project is financially viable.

Optimize Project Cost Management  

How Accurate is a ROM Cost Estimate?

ROM costs have a wider range than other construction estimating types. Since they rely on assumptions or historical data, their accuracy depends on how similar the new project is to past benchmarks.

The table below shows the typical accuracy range for ROM costs compared to other estimate types based on project stage and detail level:

Estimating Stage Accuracy Range
ROM Cost Estimate -25% to +75%
Intermediate Estimate -15% to +30%
Definitive Estimate -5% to +10%

ROM estimates are best for early-phase decisions. Always update them as scope and design evolve.

How to Calculate a ROM Cost

Rough Order of Magnitude cost calculations rely on basic data, often from similar projects, cost per square meter, or simple unit rates.

Here are the steps to create a ROM cost:

  1. Define high-level scope: Identify general functions, size, or outcomes.
  2. Choose a base unit: m², linear meters, or number of assets (e.g., hospital beds, bridges, tracks).
  3. Use benchmark rates: Pull unit costs from past projects or cost databases.
  4. Multiply for total ROM: Apply rate × quantity to get your ROM cost.
  5. Add contingency: Factor in allowances for unknowns or concept-stage risks.
  6. Document assumptions: Clearly list what’s included, excluded, and uncertain.

You can use Excel, parametric software, or platforms like Mastt to model early ROM costs quickly.

ROM Cost vs. Definitive Estimate

ROM costs support early decisions with broad estimates, while definitive estimates guide procurement and contracts. Each serves a different purpose based on project phase and detail level.

The table below compares ROM costs and definitive estimates across timing, accuracy, project scope, and use case:

Factor ROM Cost Definitive Estimate
Timing Concept phase Post-design
Accuracy -25% to +75% -5% to +10%
Scope definition Broad or assumed Fully defined
Method Historical/unit-based Detailed quantity takeoff
Use case Feasibility, funding Contracts, procurement
Approval level Preliminary Final

ROM costs guide early scope and funding decisions. Definitive estimates lock in costs for delivery and construction contracts.

What Tools Help Build ROM Costs?

Generating fast, reliable ROM costs requires tools built for early-stage estimating. These tools must handle limited data and support quick-scope modeling.

Below are the tools and platforms used for ROM cost development:

  • Mastt’s estimate modules for early cost modeling, risk visibility, and scenario planning.
  • Historical cost databases (e.g., RSMeans, Rawlinson).
  • Benchmark calculators for $/m² or per asset.
  • Excel templates with preloaded formulas and assumptions.
  • Parametric software for schools, hospitals, roads, etc.

Early-stage estimating needs tools that handle limited data and support quick-scope modeling. Mastt delivers this by letting teams build and adjust ROM costs in minutes using real benchmarks.

Optimize Project Cost Management  

How Mastt Helps Estimate ROM Costs

Mastt simplifies ROM cost estimating with tools built for early-stage planning and limited inputs. Teams can quickly model scope, apply benchmarks, and generate estimates in minutes.

Here's how Mastt Features for ROM Costs:

  • Instant concept estimates: Apply cost per square meter to early designs.
  • Historical project library: Use past projects to inform similar scope models.
  • Early risk flags: Spot funding gaps, contingency shortfalls, or incomplete scope.
  • Scenario comparisons: Test different delivery models or staging options.
  • Clear ROM dashboards: Show stakeholders' cost ranges, risks, and assumptions visually.

Mastt speeds up early estimates and improves accuracy with real data and smart visuals. That means faster decisions, fewer delays, and better project outcomes.

ROM Cost Examples in Real Projects

ROM costs help assess if a project idea fits the budget before design phases or delivery begins. These examples show how high-level estimates support fast approvals and early planning.

Below are ROM cost examples across different project types, each showing scope, unit rate, and estimated value:

Example 1: School Upgrade

  • Scope: Add 12 classrooms, canteen upgrade
  • ROM unit: $3,200/m²
  • Total area: 2,000 m²
  • ROM cost: $6.4 million + 20% contingency

Example 2: Highway Expansion

  • Scope: 5 km dual carriageway
  • ROM unit: $12M/km based on similar roads
  • ROM cost: $60 million, including land and design allowances

Example 3: New Hospital Wing

  • Scope: Surgical theatre + 80 beds
  • ROM unit: $6,500/m²
  • Area: 10,000 m²
  • ROM cost: $65 million + fit-out costs

Each example shows how ROM costs guide early scope, budget, and delivery decisions. They help teams assess feasibility before committing to design or procurement.

Common ROM Cost Pitfalls and How to Avoid Them

Skipping ROM costs creates scope, budget, and approval risks. Early decisions often lead to delays and cost blowouts without a structured estimate.

The table below outlines common ROM cost pitfalls, their causes, and how to avoid them:

Problem Why It Happens How to Solve It
Scope mismatch No alignment on inclusions/exclusions Define inclusions clearly in every ROM
Wrong unit cost Outdated or irrelevant data Use current, matched benchmarks
Skipped contingency No allowance for early-stage risks Add 20–30% contingency
Unclear documentation Missing assumptions or exclusions Document scope, rates, and sources clearly
Applied too late Estimate created after design starts Do ROM during the idea stage only

Addressing these pitfalls early keeps the project on track and stakeholders aligned. A reliable ROM cost isn’t perfect, but it must be intentional, consistent, and informed.

Final Thoughts on ROM Costs

ROM costs help construction teams lead with clarity. When used right, they shape scope, support funding, and set projects up for success. Without them, early planning turns into costly corrections.

Tools like Mastt turn ROM cost estimating into a fast, smart decision point. Try Mastt today to build fast, visual ROM estimates and get your projects off the ground faster.

Posts on this topic

Construction Cost Calculator [100% FREE Estimator]
Construction Estimating

Construction Cost Calculator [100% FREE Estimator]

Our free construction cost calculator helps you estimate accurate home, commercial, and residential building expenses. Plan your budget with precise material and labor estimates.

Construction Cost Calculator [100% FREE Estimator]

Jefbeck Eje

Powering Construction Project Management with easy-to-use tools

Start for FreeWatch Product Tour
Mastt Logo
Stay up-to-date with Mastt:
You're in the loop
Oops! Something went wrong while submitting the form.

Solutions

Use Cases

ProjectsProgram/ PortfoliosEnterprise

Roles

Project OwnersPM Consultants

Product

Dashboards & ReportingBudget & ForecastsRiskScheduleContracts & PaymentsIntegrationAll Features

Industries

Education
Transportation
Aviation
Events
Public Works
Civil
Utilities
Residential
Real Estate Development

Customers

Featured CustomerSuccess Stories

Compare

Mastt vs ProcoreMastt vs KahuaMastt vs InEightMastt vs AconexMastt vs iTWOcx

Resources

Free TemplatesWebinarsGlossaryArticlesTopicsFAQProject Management FirmsRisksHelp Pages

Company

AboutAboutConstruction Project ManagementContact UsPrivacyLegalSecurity
© Copyright 2025 Mastt.
Be part of our community
LinkedIn Icon