Australian Construction Procurement and Delivery Statistics 2026
Doug Vincent
Co-founder, CEO
Published:
Nov 19, 2026
This 2026 research breaks down construction procurement in Australia, covering the project pipeline, delivery models, contracts, cost estimates and completion.
Australia’s construction procurement and delivery decisions shape how investment becomes roads, buildings and essential services. Procurement establishes the work to be purchased and who will deliver it. During delivery, project costs, completion forecasts and compliance records show how that work is progressing.
This 2026 review brings together national construction statistics and selected government records to examine investment, contract awards and project delivery. It focuses on public construction and major infrastructure, with additional findings from residential building inspections. The evidence shows where investment is concentrated, how participation differs between selected tenders, and how project estimates and expected completion dates have changed.
What Are the Key Findings?
Planned investment
53%
of the $242 billion public infrastructure pipeline is transport
TransportBuildingsUtilities
Split bar of the $242 billion pipeline: transport 53%, buildings 32%, utilities 15%.
Transport leads, with buildings and utilities adding substantial demand
The $242 billion pipeline comprises:
Transport: $129 billion, or 53%. It is the largest category, ahead of buildings and utilities combined.
Buildings: $77 billion, or 32%. Social and affordable housing contributes $28 billion, while health projects contribute $22 billion within this category.
Utilities: $36 billion, or 15%. Additional electricity transmission projects account for much of the increase from the previous outlook.
This is a forecast of investment in major public projects across all states and territories. Its size thresholds exclude smaller projects, so it is only part of Australia’s construction market.
For procurement planning, the sector split provides a useful starting point for identifying future work. A total pipeline value alone says little about the particular design disciplines, trades or equipment that an individual project will need.
Transport makes up $129 billion, more than half of the $242 billion pipeline.
$242b
total pipeline
TransportLargest share of the pipeline
$129b53%
BuildingsIncludes $28b housing and $22b health
$77b32%
UtilitiesGrowth led by electricity transmission
$36b15%
Donut chart of Australia's major public infrastructure pipeline, $242 billion across 2024-25 to 2028-29: Transport $129 billion (53%), the largest share; Buildings $77 billion (32%), including $28 billion housing and $22 billion health; Utilities $36 billion (15%), with growth led by electricity transmission.
Major public infrastructure pipeline
Planned investment in major public projects across all states and territories, 2024-25 to 2028-29.
How Much Engineering Construction Work Is Being Delivered?
Australia recorded $37.2 billion in engineering construction work during the June quarter of 2026. The ABS release, published on 30 September 2026, measures work performed during the quarter, using seasonally adjusted volumes with a 2023–24 price reference.
Work for the public sector reached $15.8 billion in the June quarter
The national results separate work for public and private clients:
Public sector: $15,799.5 million. Work done fell 0.8% from the March quarter and 2.4% from the June quarter of 2025. This includes private contractors’ work for public clients and work performed by the public sector itself.
Private sector: $21,400.5 million. Activity fell 7.4% over the quarter and 4.6% over the year, a larger contraction than the public-sector result.
Total engineering construction: $37,200.0 million. Combined activity fell 4.7% over the quarter and 3.7% over the year.
The quarter’s decline was more pronounced in private-sector work. These inflation-adjusted engineering figures cover a different population and period from the infrastructure pipeline. They cannot be used to calculate how much of that pipeline has been completed.
Public-sector engineering work fell 0.8% in the June quarter of 2026, far less than private-sector work.
Public sector$15.8b of work done
Down 0.8%
All engineering$37.2b of work done
Down 4.7%
Private sector$21.4b of work done
Down 7.4%
Bar chart of the fall in engineering construction work done from the March to the June quarter of 2026: public sector down 0.8% to $15.8 billion ($15,799.5 million); all engineering down 4.7% to $37.2 billion ($37,200.0 million); private sector down 7.4% to $21.4 billion ($21,400.5 million).
Change in engineering construction work
June quarter 2026 compared with March quarter. Public includes private contractors building for government.
What Is the Value of Commonwealth Building-Related Procurement?
Building-related services represented $10.4 billion in reported Commonwealth contract value in 2024–25. This is the latest annual category breakdown displayed on the Department of Finance’s procurement statistics page when checked on 19 November 2026. Its AusTender extract is dated 13 August 2025.
Building-related services account for 9.9% of reported procurement value
The published category is “Building construction and support and maintenance and repair services”:
Reported value: $10,397.1 million. The aggregate includes newly reported contracts and amendments, including reductions in previously reported values.
Share of total reported procurement value: 9.9%. This is the category’s share across Commonwealth goods and services. It does not represent all Australian government construction procurement.
Building-related services made up 9.9% of reported Commonwealth contract value in 2024-25.
Almost a tenth of reported contract value
Building-related servicesAll other goods and services
$10.4 billionbuilding-related contract value
9.9%of all reported contract value
1 icon = 10% of reported contract value
Pictograph of ten contract icons, 1 icon per 10% of reported Commonwealth contract value in 2024-25. One icon, filled to just under full, is building construction and support and maintenance and repair services: 9.9%, or $10.4 billion ($10,397.1 million). These are reported contract commitments, including amendments, not annual spending.
Commonwealth building-related procurement
Reported contract commitments, 2024-25, including amendments. Contracts can span several years, so this is not annual spending.
Contract commitments can extend across several years. The total therefore measures reported contractual value, rather than expenditure during a single financial year. Finance also cautions that the introduction of value-reducing amendments in July 2024 affects comparisons with earlier years.
A contract amendment can purchase additional work or time
Commonwealth reporting guidance distinguishes the initial contract term from options exercised later. An extension or renewal can increase the reported commitment because the buyer has purchased an additional period of service.
For example, taking up an optional year of building maintenance adds service time to the contract. That increase has a different explanation from paying more to deliver the original scope. Contract reporting is more useful when the reason for an amendment is recorded alongside the amount.
What Do Brisbane’s 2026 Awards Show About Tender Participation?
Two August 2026 awards attracted different numbers of suppliers and covered very different packages of work. Brisbane City Council’s award register identifies the respondents, successful supplier, estimated or maximum value, and potential maximum term for each contract.
The sports facility attracted seven respondents, while bridge scaffolding attracted two
The selected entries show:
Pallara District Sports Facility, CW26529: seven named respondents. Epoca Constructions won the contract. Council lists an estimated or maximum value of $12,291,406 and a potential maximum term of 14 months.
Walter Taylor Bridge Stage 2 scaffolding, CW29573: two named respondents. Central Scaffolding and Rigging Services won the contract. The listed estimated or maximum value is $278,910, with a potential maximum term of 16 weeks.
7 suppliers responded to the Pallara sports facility tender, compared with 2 for the much smaller bridge scaffolding job.
Pallara sports facilityValued up to $12.3m, over up to 14 months
7
Walter Taylor Bridge scaffoldingValued up to $279k, over up to 16 weeks
2
1 icon = 1 supplier
Pictogram of named respondents in two Brisbane City Council awards approved in August 2026: Pallara District Sports Facility, CW26529, estimated or maximum value $12,291,406 (about $12.3 million), potential maximum term 14 months, 7 respondents; Walter Taylor Bridge Stage 2 scaffolding, CW29573, estimated or maximum value $278,910 (about $279 thousand), potential maximum term 16 weeks, 2 respondents. 1 icon represents 1 supplier.
Suppliers responding to two Brisbane tenders
Brisbane City Council awards, August 2026. Two examples, not a council-wide rate.
The sports facility attracted the larger field. These two awards illustrate how participation varies between packages, but they do not establish an average for Brisbane or explain why suppliers chose to bid.
Tender participation and award evaluation answer different questions
For an owner assessing competition, the useful next step is to examine comparable packages: similar work, scale and tender conditions. Combining unrelated contracts into a single bidder average would hide those differences.
How Do Delivery Models Allocate Design and Construction Responsibilities?
The delivery method determines who develops the design and how construction is organised. Victoria’s current framework distinguishes lump-sum models from cost-reimbursable models, with different arrangements within each category.
The following examples explain those responsibilities. They are selected models from the framework, rather than a ranking of model use or performance in 2026.
Construct only and design and construct place design responsibility differently
Two common arrangements within the lump-sum category are:
Construct only: The delivery agency is responsible for design, then engages a contractor to build to the detailed specification. The agency’s design work therefore precedes the main construction responsibility.
Design and construct: A single contractor undertakes detailed design and construction. The owner’s procurement documents need to make the required project outcomes clear enough for that combined responsibility to be priced and delivered.
Managing contractor and alliance models organise delivery through different relationships
Within the cost-reimbursable category:
Managing contractor: The managing contractor coordinates delivery, including completing design and construction documentation and tendering and awarding trade packages. Procurement continues through those packages as the project develops.
Alliance: The owner works with the contractor, designer and other contracted participants to design and construct the project. This places the owner within the collaborative delivery arrangement.
Delivery models differ in who designs and who builds, from separate parties to one combined team.
DesignsBuilds
Construct onlyLump-sum model
AgencyContractor
Design and constructLump-sum model
One contractor
Managing contractorCost-reimbursable model
Managing contractor coordinates both
AllianceCost-reimbursable model
Owner, contractor and designer together
A full-width bar means one party, or one team, handles both.
Diagram of who designs and who builds under selected Victorian delivery models. Construct only: the delivery agency designs and a contractor builds. Design and construct: one contractor does both. Managing contractor: coordinates both, finishing the design documents and tendering and awarding trade packages. Alliance: the owner, contractor, designer and other participants design and build together.
Who designs and who builds
Victoria's procurement framework. Shows responsibilities, not how often each model is used.
A useful model decision starts with the project’s responsibilities and unresolved risks. The model type alone cannot show how much design is complete, which risks the owner retains or when prices will be established. Those details belong in the procurement strategy and contract.
What Do Recent Reports Show About Public Project Costs?
Queensland’s latest report highlights a change in portfolio reporting. Victoria’s review tracks revisions to individual project estimates. Together, they show why a cost figure needs a clear baseline before readers can interpret a rise or fall.
Queensland’s lower reported total reflects a change in reporting coverage
Planned capital expenditure: $119.2 billion over four years. This is $2.4 billion above the previous budget’s four-year plan.
Reported project estimates: $127.8 billion, compared with $153 billion previously. The fall largely reflects changed reporting for major energy projects while their full costs are reassessed. Some entries now include spending to date and the 2026–27 allocation, with completion costs excluded.
Around half the estimated value of projects above $500 million remains in pre-procurement. Scope, delivery arrangements and cost estimates are still being developed for that work.
Queensland's reported total fell to $127.8 billion because of a reporting change, not savings.
$153b
$127.8b
2025-26 report
2026-27 report
Why it's lower: Some energy projects now leave out completion costs. The audit says scope and funding were not cut.
Bar chart of Queensland's total reported project cost estimates: $153 billion in the 2025-26 capital statement and $127.8 billion in the 2026-27 capital statement. The fall mainly reflects changed reporting for major energy projects; the audit says it does not reflect reduced scope or funding.
Queensland reported project totals
Total estimated cost of projects in each year's capital statement, compared in the November 2026 audit.
Higher estimates: 51 projects. Their combined increase against the original estimates was $16.14 billion.
Lower estimates: 22 projects. Their combined reduction was $4.83 billion, partly offsetting the increases elsewhere.
Unchanged estimates: 16 projects. Their 2025–26 estimates retained the originally published amounts.
The net increase was $11.31 billion across project histories. Some revisions occurred years before the report’s release.
51 of 89 Victorian projects now have higher cost estimates than first published.
51higher estimates+$16.14b combined
22lower estimates-$4.83b combined
16unchanged
Block size = number of projects
Net change across all 89 projects: +$11.31b
Treemap of 89 existing and completed Victorian projects, area proportional to number of projects, comparing first published estimates with 2025-26: 51 with higher cost estimates, together $16.14 billion more; 22 with lower cost estimates, together $4.83 billion less; 16 unchanged. Net increase $11.31 billion.
Victorian project cost estimates
89 existing and completed projects, first published estimate compared with 2025-26.
How Have Victorian Project Completion Forecasts Changed?
Later completion forecasts were the largest group in a separate 81-project comparison. This compares original published dates with 2025–26 forecasts and excludes new projects and those without usable dates.
Forty projects had later forecasts than originally published
40 later forecasts moved expected completion beyond the original date.
36 unchanged forecasts retained the original timing.
Five earlier forecasts brought expected completion forward.
40 of 81 Victorian projects now have later completion forecasts than first published.
40 of 81later forecasts
5earlier
36same
40later
Half-donut chart of 81 Victorian projects, comparing original completion dates with 2025-26 forecasts: 5 earlier, 36 unchanged, 40 later. These are forecast changes, not projects that finished late.
Victorian completion forecasts
81 projects, first published completion date compared with the 2025-26 forecast. Forecast changes, not late finishes.
A schedule update should make the operational consequence visible. Moving the expected opening of an asset can affect service planning, staffing and linked works. Reporting the revised date alongside the reason and affected milestones makes the change actionable.
What Do NSW’s 2026 Regional Inspections Show About Compliance?
Recent regional inspections repeatedly identified licensing and site-signage issues, with specialist-trade supervision also appearing in the South Coast findings. Building Commission NSW’s regional reports describe targeted inspections of class 1 residential sites, extending the article’s coverage beyond public infrastructure.
Three regional campaigns identified recurring licensing and signage issues
The published results are:
Far North Coast, October 2026: 74 sites inspected, 19 penalty infringement notices and 14 caution letters. Reported issues included licensing, unlicensed contracting and subcontracting, and site signage.
South Coast, September 2026: 67 sites inspected, 33 penalty infringement notices and 16 caution letters. Issues included licensing, specialist-trade supervision and site signage.
Riverina, August 2026: 86 sites inspected, 22 penalty infringement notices and 15 caution letters. Unlicensed work, contracting and subcontracting, and non-compliant signage were identified.
South Coast inspectors issued 33 penalty notices, the most of the three campaigns shown.
Penalty notices by campaign
332219
South CoastSeptember 2026 67 sites inspected
RiverinaAugust 2026 86 sites inspected
Far North CoastOctober 2026 74 sites inspected
Split bar of penalty infringement notices in three separate NSW regional inspection campaigns at class 1 residential sites in 2026: South Coast, September, 33 notices from 67 sites inspected; Riverina, August, 22 notices from 86 sites; Far North Coast, October, 19 notices from 74 sites.
Penalty notices in three NSW regional campaigns
Separate targeted inspections of homes under construction, August to October 2026. Not a statewide rate.
The recurring issues point to practical checks on who performs the work and how the site is supervised. They also show why completion photographs and progress percentages alone give an incomplete view of delivery oversight.
How Can NSW and ACT Resources Support Contract Administration?
Contract administration turns project events into documented requests, instructions and decisions. NSW and ACT resources provide correspondence organised around contract roles, helping teams record the steps between a proposed change and its resolution.
NSW suites connect correspondence with contract responsibilities
GC21 provides more than 100 sample letters for the principal’s authorised person. These sit alongside clause commentary, role descriptions and a schedule of contractual authorities, helping users locate the correspondence relevant to an event.
MW21 provides separate principal and contractor letter packs. Its resources support relatively simple or repetitive work and include commentary and a schedule of contractual authorities.
The distinction between roles matters. A contractor’s request for a change and the principal’s response record different actions. GC21’s guidance also requires sample letters to be reviewed where the contract has been amended, so the wording matches the executed agreement.
ACT design services separates claims from instructions and determinations
The ACT design services document index contains 15 collateral documents, 30 administrator letters and 30 consultant letters. The administrator pack is designated for non-Territory employees.
Time claims and responses have separate documents. Consultant letters cover initial and further extension-of-time claims. Administrator letters cover the corresponding determinations.
Variation correspondence records more than the final amount. The packs include price requests, variation orders, consultant responses, notices and claims, allowing the stages of a change to be documented separately.
The ACT design services suite has 75 documents, with separate letters for each side of a contract.
30Administrator lettersDecisions and instructions
30Consultant lettersClaims and responses
15Collateral documentsForms and agreements
1 icon = 5 documents
Pictogram of ACT design services documents by role, 75 in total, 1 icon per 5 documents: contract administrator letters 30, decisions and instructions; consultant letters 30, claims and responses; collateral documents 15, forms and agreements.
ACT design services documents by role
Letters and forms in the ACT design services contract suite, checked 19 November 2026.
The value of these resources lies in the record they help create. A change register can identify an item, but the supporting correspondence establishes what was requested, what was decided and which party took each action. The applicable contract governs the process and authority.
Conclusion
Australia’s construction programme requires owners to carry investment decisions through procurement and into completed assets. The evidence brings attention to the work between those stages: defining packages, choosing delivery responsibilities and maintaining a clear account of changes.
Good project information makes those decisions easier to assess. Investment forecasts need a defined period. Contract values need a clear scope. Revised budgets and dates need an explanation that can be traced to the project’s history.
For project teams, the priority is continuity between the procurement decision and the delivery record. When the scope, budget, programme and contract correspondence remain connected, owners are better placed to understand progress and respond when expectations change. Construction contract management software can support this by keeping contract values, changes and payments in one record that traces back to the original award.
Sources and References
The following official publications and records support the article. Sources were checked on 19 November 2026.
National investment and construction activity
Infrastructure Australia. Annual Budget Statement 2026. April 2026, page 21. Carries the major public infrastructure pipeline and sector breakdown from the 2025 market-capacity outlook.
Infrastructure Australia. 2025 Infrastructure Market Capacity Report. Published 13 November 2025. Original source for the investment outlook covering 2024–25 to 2028–29.
Australian Bureau of Statistics. Engineering Construction Activity, Australia, June 2026. Released 30 September 2026. Public- and private-sector work done, quarterly and annual movements, and the chain-volume measurement basis.
Procurement values, awards and delivery models
Department of Finance. Statistics on Australian Government Procurement Contracts. The 2024–25 category breakdown uses an AusTender extract dated 13 August 2025. Supports the building-related contract value and share, including the explanation of value-reducing amendments.
Department of Finance. Contracting & reporting, RMG 423. Supports the distinction between initial contract terms, subsequently exercised options and reported amendments.
Brisbane City Council. Closed and awarded tenders. August 2026 entries CW26529 and CW29573. Names the respondents and successful suppliers and gives the estimated or maximum contract values and potential maximum terms.
Brisbane City Council. Council tender process. Explains the comparative-price model and weighted non-price evaluation criteria.
Victorian Department of Treasury and Finance. Lump Sum procurement category. Defines construct-only and design-and-construct responsibilities within the current Victorian framework.
Victorian Department of Treasury and Finance. Cost Reimbursable procurement category. Defines managing-contractor and alliance arrangements within the current Victorian framework.
Project costs, completion forecasts and inspections
Queensland Audit Office. Major projects 2026. Tabled 16 November 2026. Supports the four-year capital plan, changed reporting of project estimates and procurement-stage findings.
Victorian Auditor-General’s Office. Major Projects Performance Reporting 2025. Tabled 4 March 2026. Supports the 89-project cost comparison and separate 81-project completion-date comparison against original published estimates.
Building Commission NSW. Targeted compliance inspections. Far North Coast, October 2026, South Coast, September 2026, and Riverina, August 2026. Provides the site, penalty-notice and caution-letter counts and reported compliance issues.
Contract-administration resources
NSW Government. GC21 Edition 2. Sample letters, clause commentary, role descriptions and contractual-authority resources.
NSW Government. Minor Works MW21. Separate principal and contractor correspondence packs, commentary and contractual-authority resources.
Infrastructure Canberra. Design service agreement and standard conditions. Source of the three document lists and the examples of time-claim and variation correspondence. Document counts reflect the index checked on 19 November 2026.
Doug Vincent is the co-founder and CEO of Mastt, the AI capital-project management platform used by governments, Fortune 500 companies, and consultancies across APAC, North America, and MENA. Before founding Mastt in 2019, he spent a decade at RPS delivering more than $2 billion in capital works, including the $2.1B Defence Navy Infrastructure program, and holds a CPSPM certification with the AIPM. He contributes content and speaks on AI in capital project delivery at Mastt.