Mastt Logo
About
Products
Blue geometric icon composed of two overlapping diamond shapes, one slightly above and behind the other.
Mastt Platform
Capital project & program management
Three black star shapes of varying sizes on a gradient blue and green background.
Agent
New
AI Agent built for project teams
Agentic AI
A simple white robot head icon with two eyes and an antenna on a dark background.
Agent
Delegate work by email, let your Agent handle the rest
White four-pointed star-shaped sparkle icon on a dark blue-gray background.
Ask
Chat with your AI Agent in real-time
Minimalist white icon of three vertical lines and a diagonal line resembling a stylized book.
Knowledge
Put your company's know-how behind every task
Three white rounded rectangles arranged in a grid on a dark blue background.
Templates
AI drafts in your templates and branded
Two interlinked chain links forming a diagonal connection on a dark gray background.
Workflows
Automate repeatable project tasks across the platform
Blue geometric icon composed of two overlapping diamond shapes, one slightly above and behind the other.
Mastt Platform
Capital project & program management
Three black star shapes of varying sizes on a gradient blue and green background.
Agent
New
AI Agent built for project teams
Projects
Dashboard interface featuring five vertical bars in blue, each with a white icon representing a document, schedule, clipboard check, chart, and user from left to right, above a calendar grid with a highlighted date and various rectangular blue and gray blocks indicating events or tasks.
Dashboard
Live visual reporting across all project data
White dollar sign centered inside a solid blue circle, representing cost or money.
Cost
Manage budgets, contracts, payments & forecasting
Blue rounded square icon with three white horizontal lines of varying length, each line aligned to form a descending stair-step pattern, symbolizing a schedule or timeline.
Schedule
Set timelines, milestones, and track delivery
Solid blue equilateral triangle.
Risk
Track risks, issues, and mitigation actions
Documents
All your files in neat folders, with AI chat
Program/Portfolio
Blue organizational chart icon with one top node connected to three lower nodes in a horizontal line.
Program
Automated roll-up of data from all projects
Contact Sales
Product Tour
Who We Serve
Business Types
Simple blue icon of a house with a triangular roof and a rectangular door in the center.
Project Owners
Control capital project outcomes with trusted oversight
Blue minimalist house icon with pointed roof and rounded-top door.
Real Estate Developers
Manage your entire portfolio with confidence
Blue generic user profile icon with a round head and rounded shoulders silhouette.
Project Management Consultant
Run professional projects from a single platform
Owner's Representative
Streamline reporting and keep every project on track
Use Cases
Project ControlsContract ManagementPMIS Software
Industries
Aviation
Education
Energy
Healthcare
Industrial
Infrastructure
Public Works
Retail
Utilities
See All Industries
Contact Sales
Product Tour
Pricing
Customers
Resources
Learn
Free Templates
Download free tools, guides, checklists, plans and more
Dashboard Examples
Download free dashboards & reports
Articles
Learn about Construction Project Management best practices
Two blue stylized books, one standing upright and the other leaning against it at an angle, each with white rectangular label areas on the covers and spines.
Topics
Full guides on the important topics around construction management
Webinars
Watch ConTech in action
SUPPORT
FAQs
Get answers for common questions
Get Help
Expert coaching, technical support and guidance
Blue shield icon with a white check mark inside, representing security or verification.
Trust Center
Learn how we protect your data and privacy.
Latest Webinar
Smarter Project Cost Management with AI, Dashboards, and ERP Data

October 1, 2026

Smarter Project Cost Management with AI, Dashboards, and ERP Data
Contact Sales
Product Tour
Log In
Australia / APAC
North America Region
MENA
Map of Southern Europe and surrounding areas showing Italy with its boot-shaped peninsula, the islands of Sicily and Sardinia, parts of France, Spain, Greece, and nearby Mediterranean Sea in blue and landmasses in green.
Rest of World
Log InStart for Free
02 9133 4355
Talk to Sales
|
Log In
Australia / APAC
North America Region
MENA
Map of Southern Europe and surrounding areas showing Italy with its boot-shaped peninsula, the islands of Sicily and Sardinia, parts of France, Spain, Greece, and nearby Mediterranean Sea in blue and landmasses in green.
Rest of World
Start for Free
Mobile Menu Icon
Resources
/
Glossary

Estimate to Complete (ETC)

Estimate to Complete (ETC) is a forecast of how much more money is needed to complete the remaining work on a project.

Topic: 
Construction Cost Tracking
Date posted: 
June 11, 2024
Date updated: 
January 29, 2026

Contents

Example H2
Confident professional man holding a tablet and smiling while standing in a modern office environment. He is dressed in a blue sweater and white collared shirt, suggesting a tech-savvy or managerial role.
Top Performers Don’t Guess. They Deliver.

Cut the stress of showing up unprepared

Start for Free

Trusted by the bold, the brave, and the brilliant to deliver the future

What is Estimate to Complete?

Estimate to Complete (ETC) is the projected cost required to finish the remaining work on a construction project based on current performance and updated cost assumptions. ETC is used to forecast final costs, flag emerging budget risk, and support more reliable cost reporting as the project progresses.

Popular
Free Template

Construction Cost Tracker

Use this FREE Construction Cost Tracker Template to monitor budgets, actuals, and cost variances. Track contracts, change orders, EAC, and payment progress for better cost control across your project.

Use this Template

What is Estimate to Complete (ETC) in Construction Project Management?

In construction project management, staying on top of costs is essential to delivering projects on time and within budget. One key tool for this is Estimate to Complete (ETC). If you’ve been wondering how to predict the remaining costs on your project, the estimate to complete formula is your go-to tool. Let’s break down what ETC is, why it matters, and how to calculate it.

What Does "Estimate to Complete" Mean?

Estimate to complete is a forecast of how much more money is needed to complete the remaining work on a project. It’s an essential part of construction cost tracking and helps answer that all-important question: How much will it cost to get the job done? Whether you're tracking a single construction project or multiple projects, ETC gives you a clear idea of future costs, enabling better planning and resource allocation.

Why is Estimate to Complete (ETC) Important?

  1. Accurate Budget Tracking: ETC lets you know if you’re on track financially, or if the project will require additional funds.
  2. Better Decision-Making: Knowing how much more is required helps you make informed decisions on resource allocation and cost control, avoiding surprises down the line.
  3. Prevents Overruns: By regularly calculating the estimate to complete, you can implement changes early and avoid large, unexpected expenses at the end of the project.
FREE TEMPLATE

How to Calculate Estimate to Complete (ETC)

There are two common ways to calculate ETC, and the right approach depends on how closely current performance matches the original plan.

ETC = Budget at Completion (BAC) – Earned Value (EV)‍

This method works best when scope, productivity, and costs are tracking as expected. It shows how much of the approved budget remains, assuming future work will follow the same cost performance as completed work.

ETC = Estimate at Completion (EAC) – Actual Cost (AC)‍

This approach is more reliable when the project has experienced cost overruns, scope changes, or productivity shifts. By using an updated estimate at completion, it reflects current conditions and provides a more realistic forecast of the funding still required to finish the project.

Example of Estimate to Complete in Project Management

Let’s say you’re managing a construction project with a total budget (BAC) of $1,000,000. So far, you’ve completed 50% of the work (EV = $500,000), but actual costs are already at $600,000 (AC). Using the second estimate to complete formula, you can calculate that you’ll need an additional $400,000 to finish the project.

Without this forecast, it’s easy to assume the project is on budget when, in reality, it’s heading for an overrun. For more tips on staying within budget, check out our guide on tracking project costs effectively.

Launch Your Free Construction Cost Tracker with Mastt  

When Should You Update Your ETC?

Construction projects are rarely static. They evolve, and so do the costs. That’s why it’s important to update your estimate to complete regularly, especially after:

  • Major project milestones or phases are completed.
  • Significant changes in project scope or timeline occur.
  • Actual costs deviate noticeably from the original plan.

Updating the ETC ensures you have an accurate picture of future spending and can help you avoid surprises at the finish line.

Related Resources

  • For a deep dive into cost management, visit our Cost Management Plan guide.
  • Learn how to streamline cost tracking with the Capital Project Cost Tracker in Excel template.
  • Use this construction cost calculator to get accurate cost estimates for your project.

Mastering estimate to complete calculations is a vital part of keeping your project on budget and on track. By regularly updating the ETC formula, you can stay ahead of potential issues and ensure a smoother journey to project completion.

A screenshot of Mastt's Project Dashboard showing financial charts and information including bar charts and donut charts
Review ETC through real-time Program Dashboards.

Posts on this topic

The Importance of Real-Time Cost Tracking in Construction
Construction Cost Tracking

The Importance of Real-Time Cost Tracking in Construction

The ability to track costs as they occur can be the difference between staying on budget and facing substantial overruns. Let’s dive into why this is so crucial and how it impacts construction projects of all sizes.

The Importance of Real-Time Cost Tracking in Construction

Jacob Gibbs

Tracking Committed Costs in Construction Projects: A Step-by-Step Guide
Construction Cost Tracking

Tracking Committed Costs in Construction Projects: A Step-by-Step Guide

Learn what committed costs are, why they matter in construction projects, and how to track them step by step to stay on budget and avoid overspending.

Tracking Committed Costs in Construction Projects: A Step-by-Step Guide

Doug Vincent

Cost Tracking vs. Cost Monitoring: A Project Management Introduction
Construction Cost Tracking

Cost Tracking vs. Cost Monitoring: A Project Management Introduction

Let’s break down project cost tracking and cost monitoring to make sure you know what you need to manage your project’s finances effectively.

Cost Tracking vs. Cost Monitoring: A Project Management Introduction

Doug Vincent

Take control of your next project

Start for FreeWatch Product Tour
Mastt Logo

Solutions

Project OwnersReal Estate DevelopersProject Management ConsultantsSmall BusinessesGovernmentOwner's Representative

Product

CPMS
ProgramDashboardCostRiskScheduleDocuments
Agent
AgentAskWorkflowsKnowledgeTemplatesAll Features

Industries

Aviation
Education
Energy
Healthcare
Industrial
Infrastructure
Public Works
Retail
Utilities
All Industries

Customers

Featured CustomerSuccess Stories

Compare

CPMS
Mastt vs ProcoreMastt vs KahuaMastt vs InEightMastt vs AconexMastt vs iTWOcx
Agent
Mastt vs Claude

Resources

ArticlesTopicsGlossaryResearchFAQContributorsEditorial ProcessFree TemplatesWebinarsProject Management FirmsRisksHelp Pages

Company

AboutAboutTeamContact UsCareersWebsite Privacy PolicyLegalSecurity
© Copyright 2026 Mastt.
Be part of our community
LinkedIn Icon