Mastt Logo
Why
Product
Product Tour
A video of Mastt sofware showing a dashboard with a map, charts and visualizations for project progress and health
Explore Mastt
Watch how Mastt is used on $25bn+ of capital improvement portfolios
REPORTING PLATFORM
Dashboards & Reporting
Contracts & Payments
Budget & Forecasts
Risks & Opportunities
Schedule
Integrations
AI
Solutions
Use Cases
Capital Projects
Programs & Portfolios
Enterprise
roles
Project Consultants
Project Owners
Industries
Education
Transportation
Aviation
Events
Public Works
Civil
Utilities
Residential
Real Estate Development
Pricing
Customers
Resources
Learn
Free Templates
Download free tools, guides, checklists, plans and more
Dashboard Examples
Download free dashboards & reports
Articles
Learn about Construction Project Management best practices
Topics
Full guides on the important topics around construction management
Webinars
Watch ConTech in action
SUPPORT
FAQs
Get answers for common questions
Get Help
Expert coaching, technical support and guidance
Trust Center
Learn how we protect your data and privacy.
Log In
Australia / APAC
North America Region
MENA
Rest of World
Log InSee Product Tour
02 9133 4355
Talk to Sales
|
Log In
Australia / APAC
North America Region
MENA
Rest of World
Start for Free
Mobile Menu Icon
Resources
/
Glossary

WBS (work breakdown structure)

A hierarchical decomposition of a Capital Project budget. Components of a WBS for include phases like design, procurement, construction, and commissioning,

Topic: 
Project Scheduling

Contents

Example H2
Related blog post

Key Project Milestones [Free List]: Using Milestones for Better Project Scheduling

Discover how project milestones can transform your scheduling process and keep construction projects on track. This guide covers milestone meaning, practical examples, and tips for setting effective milestones to ensure project success from start to finish!

What is WBS? WBS meaning explained

A Work Breakdown Structure (WBS) is a key project management tool that involves breaking down a project into smaller, more manageable components or tasks. This hierarchical decomposition helps project managers and teams organize and define the total scope of the project, ensuring that all necessary work is identified and accounted for.

Popular
Free Template

Construction Cost Tracker

Use this FREE Construction Cost Tracker template for clear, efficient oversight of your capital project's financials.

Use this Template

What is a WBS?

A Work Breakdown Structure (WBS) is a detailed, hierarchical tree structure that breaks down a project into smaller, more manageable parts. Each level of the WBS represents an increasingly detailed definition of project work. The primary purpose of a WBS is to simplify project planning, execution, monitoring, and control by organizing the work into smaller, manageable sections.

About WBS

The WBS is a critical component of project management, providing a clear and structured approach to organizing project tasks. By breaking down the project into smaller tasks, the WBS helps ensure that all aspects of the project are covered, enabling more accurate planning and resource allocation. It serves as a foundation for various project management activities, including scheduling, budgeting, risk management, and performance tracking.

Best Practices for Creating a WBS

  • Define the Project Scope: Clearly define the project scope to understand the overall objectives and deliverables. This will help in identifying the major components of the project.
  • Use a Hierarchical Structure: Develop the WBS using a hierarchical structure where the project is divided into major deliverables, which are then further broken down into smaller tasks and subtasks.
  • Involve Stakeholders: Engage relevant stakeholders, including project owners, project managers, and team members, in the development of the WBS to ensure all perspectives are considered.
  • Maintain Consistency: Use consistent terminology and formats throughout the WBS to avoid confusion and ensure clarity.
  • Focus on Deliverables: Structure the WBS around deliverables rather than activities to ensure that the focus remains on what needs to be achieved rather than how it will be done.
  • Review and Refine: Regularly review and refine the WBS as the project progresses to ensure it remains relevant and accurate.

WBS vs. Project Schedule

  • Work Breakdown Structure (WBS): A WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team. It focuses on defining and organizing the work into manageable sections.
  • Project Schedule: A project schedule is a detailed plan that outlines when and how the project tasks will be performed. It includes timelines, milestones, and dependencies between tasks.

When to Use a WBS

  • Project Planning: During the initial planning phase to break down the project scope into detailed tasks and define the work required to achieve the project objectives.
  • Resource Allocation: To allocate resources effectively by identifying the specific tasks and deliverables that need to be completed.
  • Risk Management: To identify potential risks by understanding the detailed components of the project and where issues may arise.
  • Progress Monitoring: To track project progress and performance by comparing the completed work against the defined tasks and deliverables.
  • Budgeting and Cost Management: To develop accurate budgets and manage costs by understanding the detailed work and resources required for each task.

By implementing an effective Work Breakdown Structure, project managers can enhance their ability to plan, execute, and control projects, leading to improved project outcomes and successful delivery.

How Mastt Helps with WBS

Mastt provides a comprehensive platform that supports the efficient creation and management of Work Breakdown Structures. Here’s how Mastt can assist:

  • WBS Development Tools: Mastt offers tools to create detailed WBS hierarchies, allowing project managers to break down complex projects into manageable tasks.
  • Integration with Project Planning: The platform integrates WBS with overall project planning, ensuring that all tasks are aligned with project objectives and timelines.
  • Resource Management: Mastt helps allocate resources effectively by linking WBS elements to specific resources, ensuring optimal utilization.
  • Risk Management: By offering robust risk management tools, Mastt enables project managers to identify and mitigate risks associated with each WBS element.
  • Performance Tracking: Mastt's dashboard provides real-time insights into the progress of each WBS element, facilitating effective monitoring and control.
  • Budget Management: The platform supports detailed budgeting and cost management by associating costs with specific WBS elements, ensuring accurate financial tracking and reporting.

WBS Template in Mastt

By leveraging Mastt, project managers can enhance their WBS processes, leading to more efficient project reporting.

A screenshot of a software produce showing WBS and WBS breakdown
WBS template in Mastt showing a work breakdown structure

WBS Reporting in Mastt

Reporting for project managers is automated, including visualization of the WBS.

An project dashboard in Mastt

Posts on this topic

Schedule Risk Analysis Explained
Project Scheduling

Schedule Risk Analysis Explained

Learn how schedule risk analysis helps you spot and fix delays in projects, so you can plan better timelines and finish on time without extra costs.

Schedule Risk Analysis Explained

Jackson Row

Schedule Optimization: Tips and Tricks for Finishing Early
Project Scheduling

Schedule Optimization: Tips and Tricks for Finishing Early

Learn simple schedule optimization tips to finish construction projects early, save money, avoid delays, and keep your team and clients happy.

Schedule Optimization: Tips and Tricks for Finishing Early

Anna Marie Goco

What is a Milestone Schedule? 6 Easy Steps to Create One
Project Scheduling

What is a Milestone Schedule? 6 Easy Steps to Create One

A milestone schedule breaks projects into key checkpoints for better tracking and alignment. Learn how to create one, manage deadlines, and improve stakeholder communication.

What is a Milestone Schedule? 6 Easy Steps to Create One

Jamie Cerexhe

Powering Construction Project Management with easy-to-use tools

Start for FreeWatch Product Tour
Mastt Logo
Stay up-to-date with Mastt:
You're in the loop
Oops! Something went wrong while submitting the form.

Solutions

Use Cases

Managing Contract Variations
Project Timeline Management
Managing Construction Contracts
Client Dashboard
Construction Client Management
All Use Cases

Product

Dashboards & ReportingBudget & ForecastsRiskScheduleContracts & PaymentsIntegrationAll Features

Industries

Education
Transportation
Aviation
Events
Public Works
Civil
Utilities
Residential
Real Estate Development
All Industries

Customers

Featured CustomerSuccess Stories

Compare

Mastt vs ProcoreMastt vs KahuaMastt vs InEightMastt vs AconexMastt vs iTWOcx

Resources

Free TemplatesWebinarsGlossaryArticlesTopicsFAQProject Management FirmsRisksHelp Pages

Company

AboutAboutConstruction Project ManagementContact UsPrivacyLegalSecurity
© Copyright 2025 Mastt.
Be part of our community
LinkedIn Icon