Mastt Logo
Why
Product
Product Tour
A video of Mastt sofware showing a dashboard with a map, charts and visualizations for project progress and health
Explore Mastt
Watch how Mastt is used on $25bn+ of capital improvement portfolios
REPORTING PLATFORM
Dashboards & Reporting
Contracts & Payments
Budget & Forecasts
Risks & Opportunities
Schedule
Integrations
AI
Solutions
Use Cases
Capital Projects
Programs & Portfolios
Enterprise
roles
Project Consultants
Project Owners
Industries
Education
Transportation
Aviation
Events
Public Works
Civil
Utilities
Residential
Real Estate Development
Pricing
Customers
Resources
Learn
Free Templates
Download free tools, guides, checklists, plans and more
Dashboard Examples
Download free dashboards & reports
Articles
Learn about Construction Project Management best practices
Topics
Full guides on the important topics around construction management
Webinars
Watch ConTech in action
SUPPORT
FAQs
Get answers for common questions
Get Help
Expert coaching, technical support and guidance
Trust Center
Learn how we protect your data and privacy.
Log In
Australia / APAC
North America Region
MENA
Rest of World
Log InSee Product Tour
02 9133 4355
Talk to Sales
|
Log In
Australia / APAC
North America Region
MENA
Rest of World
Start for Free
Mobile Menu Icon
Resources
/
Glossary

Completion Date

The completion date is the specific day when all project tasks are finalized, and the project's objectives are fully achieved. This date is crucial for effective project scheduling, as it helps in planning resources, setting milestones, and managing stakeholder expectations. Accurately determining the completion date ensures timely delivery and successful project outcomes.

Topic: 
Project Scheduling

Contents

Example H2
Related blog post

Project Completion: Everything You Need to Know Before It Happens!

Explore everything you need to know for a flawless project closeout! This guide covers essential steps, tips, and documentation to ensure a smooth project completion that leaves clients impressed and sets you up for success.

What is Completion Date?

The completion date is the specific day when all project tasks are finalized, and the project's objectives are fully achieved. This date is crucial for effective project scheduling, as it helps in planning resources, setting milestones, and managing stakeholder expectations. Accurately determining the completion date ensures timely delivery and successful project outcomes.

Popular
Free Template

Use this Template

What is the difference between the completion date and the possession date in construction projects?

In construction, the completion date is when all construction work is done and the project meets the agreed standards. The possession date is when the owner or client officially takes ownership of the property. These dates might be the same, but sometimes possession happens later to allow for inspections or permits. Knowing both dates helps with better project planning and scheduling.

How is the estimated completion date determined in project scheduling?

The estimated completion date is calculated by breaking down all project tasks, estimating the time needed for each, and considering available resources. Tools like a Gantt chart and timelines help map out when each part of the project should be finished. This process helps set a realistic date to guide the project’s progress and ensure on-time completion.

Why is setting an anticipated completion date important in project management?

Setting an anticipated completion date is important because it gives a clear deadline, helping with budgeting, resource planning, and keeping everyone informed. This date sets expectations and allows managers to track progress. By checking progress against the anticipated completion date, managers can spot delays early and take action to keep the project on track.

Posts on this topic

Schedule Risk Analysis Explained
Project Scheduling

Schedule Risk Analysis Explained

Learn how schedule risk analysis helps you spot and fix delays in projects, so you can plan better timelines and finish on time without extra costs.

Schedule Risk Analysis Explained

Jackson Row

Schedule Optimization: Tips and Tricks for Finishing Early
Project Scheduling

Schedule Optimization: Tips and Tricks for Finishing Early

Learn simple schedule optimization tips to finish construction projects early, save money, avoid delays, and keep your team and clients happy.

Schedule Optimization: Tips and Tricks for Finishing Early

Anna Marie Goco

What is a Milestone Schedule? 6 Easy Steps to Create One
Project Scheduling

What is a Milestone Schedule? 6 Easy Steps to Create One

A milestone schedule breaks projects into key checkpoints for better tracking and alignment. Learn how to create one, manage deadlines, and improve stakeholder communication.

What is a Milestone Schedule? 6 Easy Steps to Create One

Jamie Cerexhe

Powering Construction Project Management with easy-to-use tools

Start for FreeWatch Product Tour
Mastt Logo
Stay up-to-date with Mastt:
You're in the loop
Oops! Something went wrong while submitting the form.

Solutions

Use Cases

Managing Contract Variations
Project Timeline Management
Managing Construction Contracts
Client Dashboard
Construction Client Management
All Use Cases

Product

Dashboards & ReportingBudget & ForecastsRiskScheduleContracts & PaymentsIntegrationAll Features

Industries

Education
Transportation
Aviation
Events
Public Works
Civil
Utilities
Residential
Real Estate Development
All Industries

Customers

Featured CustomerSuccess Stories

Compare

Mastt vs ProcoreMastt vs KahuaMastt vs InEightMastt vs AconexMastt vs iTWOcx

Resources

Free TemplatesWebinarsGlossaryArticlesTopicsFAQProject Management FirmsRisksHelp Pages

Company

AboutAboutConstruction Project ManagementContact UsPrivacyLegalSecurity
© Copyright 2025 Mastt.
Be part of our community
LinkedIn Icon