Guide to AIA G703 for PMs, Owners, and Contractors

Anna Marie Goco
By
Anna Marie Goco
Contributor:
Published:
Oct 22, 2025
Updated:
Oct 23, 2025
Guide to AIA G703 for PMs, Owners, and Contractors

The AIA G703 is a form from the American Institute of Architects (AIA) used to track work progress and payment details on a project. It lists each task, its value, and what’s been completed or billed so far. A clear and accurate G703 helps project managers, owners, and contractors stay aligned, which speeds up payment approvals and reduces disputes.

In this article, you’ll learn what the AIA G703 is, how it works, and how to fill it out correctly so payments move faster and reviews stay smooth.

TL;DR
The AIA G703 is a standard form from the American Institute of Architects used in AIA Billing to track project progress and payments. It lists each line item’s value, work completed, and materials stored. Accurate completion speeds up approvals and keeps construction payments transparent and dispute-free.

What is AIA G703?

The AIA G703, also called the Continuation Sheet, is an official payment tracking form created by the American Institute of Architects. It is used with the AIA G702 Application and Certificate for Payment as part of the AIA Billing process.

The form lists the work completed, stored materials, and costs tied to each line item in a construction project. This structure gives project managers, owners, and contractors a clear view of progress and costs. It also helps verify that payments match completed work, reducing review time and disputes.

Example of the official AIA G703 form used for documenting project progress and payment details.
Used with the AIA G702, the AIA G703 helps standardize payment applications and ensure billing accuracy.

How the AIA G703 Fits into Construction Payment Applications

The AIA document G703 works hand in hand with the AIA G702 to complete a construction pay application. The G702 gives the summary, while the G703 provides the detailed breakdown behind those numbers.

  • AIA G703 (Continuation Sheet): Lists each line item of work with its scheduled value, work completed, materials stored, and balance to finish. It supports the G702 by showing how the total payment request was calculated.
  • AIA G702 (Application and Certificate for Payment): Summarizes the total amount due for the current period and includes the contractor’s certification and architect’s approval.

Always reconcile your G703 totals with the G702 before submitting. Even a slight mismatch can delay payment approval for weeks. Review both forms together to catch discrepancies early and keep cash flow steady.

What are the Key Sections of the AIA G703

The AIA G703 is divided into two main parts: the Header Section and the Table of Work and Scheduled Values. Each section serves a specific purpose in documenting progress payment details.

  • Header Section: Includes basic project information such as project name, number, application number, date, and billing period. These details must match the information on the AIA G702 to keep pay applications consistent and traceable.
  • Table of Work and Values: Lists each line item of work, its scheduled value, work completed, materials stored, percentage of completion, and retainage. This section forms the core of the document and shows how each part of the project contributes to the total payment request.

Accuracy in both sections is critical. Always double-check that your Header details match the G702 exactly before filling out the Table of Work and Values. Reviewers often reject applications for simple header inconsistencies, even when the payment data is correct.

How to Fill Out the Table of Work and Values of the G703 Form

To fill out the AIA G703 form, complete each of the nine columns (A through I) with accurate details about the work performed, materials stored, and costs to date. Each column builds on the next to show how much progress has been made and how much payment is due.

Here’s how to complete each one:

Column A: Item Number

This column is for numbering each line item of work in your continuation sheet. For simple projects, you can use a straightforward sequence like 1, 2, 3. On larger or more complex jobs, use the CSI MasterFormat numbering system. It’s the same index used across construction specifications, so it keeps everyone aligned on what each line refers to.

A consistent numbering system is key for tracking progress across multiple billing periods. It also helps reviewers quickly find supporting documentation, such as invoices or inspection reports, that match the same item number.

AIA G703 form showing Column A labeled “Item Number”

Column B: Description of Work

Column B briefly describes what each line item covers. Keep descriptions clear and consistent with your schedule of values and scope of work. For example, instead of writing “Framing,” use “Interior metal stud framing, Level 1-3.” The extra detail prevents confusion later during review or auditing.

Well-written descriptions also protect you if questions arise during payment review. When your description matches your contract language, it’s easier to justify the cost and avoid back-and-forth with the general contractor or project owner.

AIA G703 continuation sheet highlighting Column B

Column C: Scheduled Value

In Column C, you enter the total dollar value assigned to each line item. This number comes from your approved schedule of values and should match it exactly. It represents the original budgeted cost for that scope of work.

These numbers usually stay fixed unless a change order adjusts the value. If you change a value, always attach supporting documentation and update your schedule of values to match.

💡 Pro Tip: Keep a master log of all change orders that modify your scheduled values. During billing, cross-check the log before submitting. A single outdated value can throw off your totals and trigger a resubmission.
AIA G703 form displaying Column C

Column D: Work Completed from Previous Applications

Column D tracks all work completed and billed before the current pay period. You’ll carry these amounts forward from the previous G703 by adding Columns D and E from that sheet. If this is your first application, leave it blank.

Be precise here. This number is your payment history. It should reflect the value of installed work only, not retainage or stored materials. If you include materials here, you’ll risk double-counting in Column F.

AIA G703 continuation sheet highlighting Column D

Column E: Work Completed This Period

Enter the value of the work performed during the current billing period. This number should reflect only what was physically completed on-site, verified through inspections, field reports, or progress photos.

Many contractors overestimate this figure to improve cash flow, but that’s risky. Overbilling can cause future reconciliation issues and damage trust with the project team.

AIA G703 form showing Column E, “Work Completed This Period,”

Column F: Materials Presently Stored

Use this column to show the value of materials purchased and stored on-site or in approved off-site facilities but not yet installed. Only include materials backed by proper documentation, like delivery receipts, invoices, or storage photos.

⚠️ Be cautious: Project owners often verify stored materials physically before releasing payment. Listing materials not yet delivered can lead to payment delays or even rejections.
AIA G703 highlighting Column F “Materials Presently Stored”

Column G: Total Completed and Stored to Date

Add Columns D, E, and F to get the total value of all work and materials to date. Reviewers use this number to verify the total amount earned so far against the scheduled value in Column C.

Accuracy here matters because this figure connects directly to both the G702 summary and your project’s financial records. A single formula error can cascade through your payment app totals.

AIA G703 form displaying Column G, “Total Completed and Stored to Date”

Column G%: Percentage of Completion

This column shows the completion percentage for each line item. Calculate it by dividing Column G (Total Completed and Stored) by Column C (Scheduled Value), then multiplying it by 100.

Owners and lenders often focus on this column. It’s a quick indicator of project health. Make sure it matches the field progress and updated schedules to avoid red flags during review.

AIA G703 highlighting Column G percentage section

Column H: Balance to Finish

Column H represents the amount left to complete each line item. Subtract Column G from Column C to get the remaining balance. It’s a useful snapshot for forecasting costs and progress toward project completion.

Accurate balance-to-finish values also help project managers plan manpower, materials, and cash flow for upcoming work.

AIA G703 form showing Column H, “Balance to Finish”

Column I: Retainage

Retainage represents the portion of payment withheld until certain milestones or completion. Use this column only when variable retainage applies, such as when the rate drops after substantial completion or applies differently to labor and materials.

If your retainage rate is fixed, it’s usually calculated on the G702 instead. Always confirm your contract terms before entering values here.

💡 Pro Tip: Track retainage separately from your regular billing records. When the project nears completion, having clear retainage documentation speeds up final payment and reduces closeout disputes.
AIA G703 highlighting Column I, “Retainage,”

How to Review and Approve the AIA G703 as a Project Manager or Owner

To review and approve the AIA G703, check that every number, description, and total aligns with the project’s schedule of values, contract terms, and actual progress on site. The goal is to verify that payment requests reflect real work performed and stored materials.

Here’s how to review it step by step:

Step What to Check Why it Matters
1. Verify Project and Application Details Confirm the project name, number, billing period, and application number match the AIA G702. Even small mismatches, like a wrong date or version, can cause accounting or audit issues.
2. Confirm Line Item Descriptions and Quantities Ensure descriptions match the approved schedule of values and that all expected scopes are listed. Missing or mislabeled line items often lead to rejected payment applications.
3. Review Scheduled Values and Change Orders Check that Column C matches the approved contract or any updated change orders. Prevents billing errors and ensures costs reflect approved changes.
4. Check Completed Work and Stored Materials Match Columns D, E, and F with site reports or inspection data. Ask for proof of stored materials like receipts or photos. Confirms that billed quantities reflect real progress and verified materials.
5. Validate Totals and Percentages Recalculate Columns G and G% for accuracy by dividing total completed (G) by scheduled value (C). Helps spot math errors or sudden progress jumps that may need explanation.
6. Confirm Retainage and Remaining Balances Review Columns H and I to ensure the balance to finish and retainage follow contract terms and match the G702. Keeps withheld payments and project completion values consistent.
7. Cross-Check with the AIA G702 Compare totals between the G703 and G702 to ensure they roll up correctly. Ensures both documents align before final certification or approval.
8. Document and Approve Sign, date, and file all review notes, inspection records, and correspondence. Creates an audit trail and protects against future payment disputes or claims.
💡 Pro Tip: Don’t rely only on the contractor’s math. Run your own quick check using a copy of the G703 or spreadsheet. Independent verification not only catches calculation errors but also shows financial diligence to lenders and auditors.

How Much is the AIA G703 Form?

The cost of the AIA G703-1992 starts at $49.99, directly from the AIA through its online document service, AIA Contract Documents (AIA CD).

The AIA offers two main options:

  • One-time-use document: Priced around $49.99, this option allows you to create, edit, and finalize a single AIA G703 form within 365 days of purchase.
  • Annual subscription: Costs about $2,199.99 per user per year and provides unlimited access to all 200+ AIA contract documents, including the G702 and G703 forms.

Because the G703 is a copyrighted form, you’ll either need to purchase it through AIA or use a licensed third-party template. Many firms offer “AIA-style” templates for free, but owners, lenders, or architects may not accept these without prior approval.

For more information or to obtain the AIA G703 form, interested parties can visit the official American Institute of Architects website or authorized distributors of AIA contract documents.

Getting Payments Right with the AIA G703

The AIA G703 is where accuracy meets accountability. A well-prepared AIA G703 keeps your billing clean and your project running smoothly. It connects field progress to financial tracking so everyone can see the same picture. With one clear document, you cut through confusion, speed up reviews, and keep cash flow predictable from start to finish.

FAQs About the AIA G703

No. The AIA G703 is a copyrighted form from the American Institute of Architects and requires purchase or licensed access. Some websites offer free "AIA-style" templates online, but these are not official and may not be accepted by owners or lenders.
Yes. Subcontractors often prepare their own G703 for review by the general contractor. The GC then consolidates them into the full project payment application submitted to the owner or architect.
If the totals don't align, the payment application is usually sent back for correction. Reviewers check that the G703 breakdown supports the summary numbers in the G702 before approving payment.
Not always, but you should confirm in writing that a substitute worksheet meets the same level of detail and approval criteria as the G703. Otherwise, owners, lenders, or auditors may flag deviations from the standard and delay payment.
Typically, it's updated every billing cycle, which is usually monthly. Keeping it current ensures that payments reflect accurate progress and stored material values.
Topic: 
AIA Billing
Anna Marie Goco

Written by

Anna Marie Goco

Anna is a seasoned Senior Content Writer at Mastt, specialising in project management and the construction industry. She leverages her in-depth knowledge to create valuable content that helps professionals in these fields. Through her writing, she contributes to the company's mission of empowering project managers and construction professionals with practical insights and solutions.

LinkedIn Icon

Contributions by

LinkedIn Icon
Back to top

Supercharging Construction Project Management with AI Powered Tools